August 7, 2026
The Montana Department of Transportation (MDT), in partnership with Schellinger Construction, continues active roadwork on U.S. Highway 2 (US 2) near Essex.
The Stanton – Essex Pavement Preservation project will improve approximately 12 miles of roadway, beginning near Stanton Creek and extending southeast to just beyond the Middle Fork Flathead River bridge.
Milling and paving has concluded as of this week. Starting the week of August 10, crews anticipate installing rumble strips and updating signage within the work zone. Roadwork will take place during the day.
Motorists should continue to expect single-lane closures and reduced speeds in active work zones. Traffic signals and pilot cars are directing traffic. Please use caution when traveling through the project area.
Over the next few months, work on this project includes applying a seal and cover (chip seal), installing rumble strips, completing bridge repairs, updating pavement markings, and upgrading guardrail. These improvements will help extend the life of the roadway, enhance safety, and provide a more reliable travel experience for everyone who uses this corridor.
Additional updates will be provided as construction progresses.
July 17, 2026
The Montana Department of Transportation (MDT), in partnership with Schellinger Construction, will kick off guardrail replacement, milling, and paving on U.S. Highway 2 (US 2) near Essex.
The Stanton – Essex Pavement Preservation project will improve approximately 12 miles of roadway, beginning near Stanton Creek and extending southeast to just beyond the Middle Fork Flathead River bridge.
Starting Sunday, July 19 at 7 p.m., active construction will take place 24-hours a day. Milling operations will occur overnight Sunday night through Thursday night, with paving during the week, Monday through Friday.
Milling and paving will create additional wait times for motorists. Please plan for at least 15-minute delays when traveling through the work zone. Crews will be milling and paving starting at the west end of the project and will move east over the next few weeks.
Motorists should expect single-lane closures and reduced speeds in active work zones. Please follow posted signage and use caution when traveling through the project area.
The project team recognizes that U.S. Highway 2 is a major route for visitors traveling to and from Glacier National Park. MDT is working to minimize disruptions as much as possible while safely and efficiently completing critical roadway improvements.
If you have questions or concerns, please email Becca at