Montana Department of Transportation

Traveler Information

Travel Conditions

Construction Report

June 15, 2018 at 04:44 PM

This report is available by telephone at 511 or 1-800-226-7623. For the hearing impaired, call the TTY number 1-800-335-7592.

For additional information call (406) 444-6372

TRAFFIC FINES DOUBLE in highway work zones. The law also sets fines and jail sentences for reckless endangerment of highway workers.

MINOR DELAYS (up to ten minutes) can be expected through these projects with anything over ten minutes being noted in the description. Watch for equipment, flaggers, and workers along the road. Expect reduced speed limits.


Active Construction Projects

FRNT.RD/I-90 - Mile Marker 0 to 5.2
HAUGEN-DEBORGIA FRONTAGE ROAD.
EXPECT: SINGLE LANE CLOSURES, INTERSECTION WORK, USE I-90 AS DETOUR.
EXPECT: Overlay activities; Width Restriction of 12 feet; Delays up to 15 minutes; Fresh Oil; Loose Gravel; Reduced Speeds of 35 MPH; Pilot Cars; Rough Roadway Surface; Single Lane Traffic; Grooved Surface; Flaggers; Motorcycles Consider Alt Route.
I-15 - Mile Marker 37.9 to 45.9
Red Rock - Clark Canyon.
Shoulder work including placing concrete curb and fog sealing the shoulders of the roadway will take place.
EXPECT: Shoulder activities.
I-15 - Mile Marker 123 to 126.5
One mile east of Rocker (Exit 122).
I-15/I-90 Northbound/Eastbound lanes will be closed for bridge replacement work.
***On Monday, June 11th, 2018, traffic will be detoured onto Montana Street for a short time beginning at 9:00am. Wide load accommodations may be delayed due to detour.
*A 12 foot width restriction is in effect.
**Staging areas are available on each end of the project for loads between 12 and 18 feet in width. These loads will be escorted through the project site Monday through Thursday each week, between 9:30 am and 10:30 am Eastbound milepost 123.5 and 10:30 am to 11:30 am for Westbound traffic milepost 126.5.
For additional information call 406-490-8390.
**32- J loads (those greater than 18 feet wide, 150 feet long, or 17 feet high) must contact the Prime Contractor at (406) 490-8390 Monday - Friday, 8:00 am to 5:00 pm, before traveling to make special arrangements to be escorted through the project site on a case-by-case basis. 32- J carriers will be required to enter into a written agreement with the prime contractor to receive trip permits. All carriers may also consider use of alternate routes.
EXPECT: Bridge activities; Width Restriction of 12 feet; Reduced Speeds of 45 MPH; Single Lane Traffic.
I-15 - Mile Marker 157.8 to 158.2
Basin to Boulder, Rock Slope - West of Basin.
*Work in progress at the High Ore Interchange, milepost 160.4. I-15 traffic will be detoured to the interchange on and off ramps.
*Two way traffic in northbound lanes.
**Traffic may be stopped for up to 20 minutes resulting in 30 minute delays. These delays will occur between 7:00 am and 5:00 pm Monday through Saturday.
**A 12 foot width restriction is in effect.
***Staging areas are available on each end of the project for loads between 12 and 18 feet in width. These loads will be escorted through the project site 8:30 am to 9:30 am Southbound and then 9:30 am to 10:30 am Northbound. For additional information call 406-490-8390.
**32- J loads (those greater than 18 feet wide, 150 feet long, or 17 feet high) must contact the Prime Contractor at (406) 490-8390 Monday - Friday, 8:00 AM to 5:00 PM, before traveling to make special arrangements to be escorted through the project site on a case-by-case basis. 32- J carriers will be required to enter into a written agreement with the prime contractor to receive trip permits. All carriers may also consider use of alternate routes.
EXPECT: Bridge activities; Width Restriction of 12 feet; Delays up to 30 minutes; Detour; Reduced Speeds of 45 MPH; Single Lane Traffic; Traffic Control by Signal Lights; Flaggers.
I-15 - Mile Marker 175 to 177
I-15 Culvert - Jefferson City.
**There is single lane traffic from Jefferson City to approximately two-mile South.
There is a 12 foot width restriction in effect. Staging areas are available for loads between 12 and 18 feet wide.
**The northbound staging area is north of Boulder Interchange (mp 165)
**The southbound staging area is north of Jefferson City Interchange (mp 177).
Wide loads will be escorted through the project between 9 AM - 11 AM daily. 32-J Loads (those over 18 feet wide, 150 feet long, 17 feet high) must contact the Prime Contractor at (406) 490-8390 Monday thru Friday between 8:00 AM and 5:00 PM prior to traveling to make special arrangements to be escorted through the project site on a case-by-case basis.
**32- J carriers will be required to enter into a written agreement with the prime contractor to receive trip permits. All carriers may also consider use of alternate routes.
EXPECT: Reconstruction activities; Width Restriction of 12 feet; Reduced Speeds of 45 MPH; Single Lane Traffic.
I-15 - Mile Marker 239 to 240
Dearborn River Bridge Southbound.
Bridge inspection in progress. Single lane closure.
EXPECT: Bridge activities; Reduced Speeds of 45 MPH; Single Lane Traffic; Single Lane Closures.
I-15 - Mile Marker 244 to 246
THE CANYON INTERCHANGE.
Rock Fall Mitigation - Traffic may be stopped for up to 30 minutes at a time between 5PM - 7PM for wide load passages. Loads over 12 feet wide will be piloted through the project Monday - Thursday between 5PM - 7PM.
The staging areas are as follows:
* Northbound is at MM 243.2
* Southbound is at MM 247.
*** 32-J loads must contact the Prime Contractor at (406) 490-8390 Monday - Friday 8AM - 5PM, before traveling to make special arrangements to be escorted through the project site on a case-by-case basis
EXPECT: Miscellaneous activities; Width Restriction of 12 feet; Delays up to 30 minutes; Detour; Reduced Speeds of 55 MPH; Single Lane Traffic; Single Lane Closures; Road Closure.
I-15 - Mile Marker 309.2 to 323
4 miles south of Dutton to 10 miles north.
Weather permitting, the contractor plans to seal the northbound Teton River bridge.
EXPECT: Bridge activities; Delays up to 10 minutes; Reduced Speeds of 35 MPH; Single Lane Closures.
I-15 - Mile Marker 363.4 to 363.6
I-15 South Shelby Interchange Exit 363.
Bridge preservation work in progress. Width restriction of 13-feet is in place with the closure of the northbound bridge. Crossovers are in place. Expect two-lane, two-way traffic in the southbound lane of I-15 a mile before and a mile after the 363 exit. There are wide load staging areas located north and south of Shelby. Wide loads will be escorted through between 8:00 am and 10:00 am daily Monday through Thursday. No wide loads will be allowed through Friday and Saturday.
EXPECT: Bridge activities; Width Restriction of 13 feet; Reduced Speeds of 35 MPH; Single Lane Traffic; Single Lane Closures; Road Closure; Intersection Work.
I-90 - Mile Marker 40 to 70
9 Miles West of Superior to 5 Miles West of Alberton.
EB Crystal Spring Exit 65.0 ramps are closed for construction season. Use WB Crystal Springs ramps to access Crystal Springs.
***Staging and piloting activity will take place Monday thru Thursday. Oversized loads missing the designated piloting times will be required to wait until the next opening to be escorted through the project.***
**There is a 16-foot width restriction on I-90 in both directions from mile post 41.0 to 44.7. All loads greater than 16 feet wide will need to plan an alternate route.
**There is a 12 foot width restriction, between mile post 62.8 and 71.6. Wide loads between 12 to 16 feet wide will be piloted through this area.
*EASTBOUND LOADS between 12 and 16 feet in width are required to stage in the signed staging area at the Quartz Rest area at mile post 58 at 6 a.m. MST.,
*WESTBOUND LOADS between 12 and 16 feet in width are required to stage in the signed staging area at the Alberton Parking area mile post 72 at 7 a.m. MST.
****All Wide Loads MUST contact Mountain West Holding:406-239-1304 for piloting 24 hours in advance.****
These restrictions will remain in place until the Fall of 2018
EXPECT: Bridge activities; Width Restriction of 16 feet; Reduced Speeds varying from 35 to 55 MPH; Single Lane Traffic; Flaggers.
I-90 - Mile Marker 80 to 170
Old Hwy 10 St. Regis. I 90 Bridges Mile Post 80 to 170.
Bridge Deck repairs and overlay.
Mile Marke 33 WB & Nine Mile area Mile Markers 80-109,
*Wide Load Detour at St. Regis
***Starting on June 19th there will be a 10 foot width restriction for the St Regis and Clark Fork river Bridge. The width restriction will be in place around the clock until July 20th for Bridge deck repairs.***
Bridge deck repairs and bridge deck overlays on I 90 will be on going between mile post 80 and 109 through the end of June.Workers present on Bridge Structures.
EXPECT: Bridge activities; Width Restriction of 16 feet; Detour; Reduced Speeds varying from 35 to 55 MPH; Single Lane Closures; Traffic Control by Signal Lights; Flaggers.
I-90 - Mile Marker 84 to 94.4
Between Wye and Huson.
Two lane, two way traffic.
There is no pilot car activity at this time.
EXPECT: Median activities; Width Restriction of 14 feet; Reduced Speeds of 65 MPH; Single Lane Closures.
I-90 - Mile Marker 105.4 to 106.4
Van Buren St Interchange E&W.
Van Buren St Construction will be controlled by flaggers in both directions. WB I-90 Traffic will be reduced to 1 lane for the forseeable future. Construction will continue to 24 hours per day June 11 thru 15. The westbound off ramp will be closed June 13 thru June 25. Drivers are encouraged to plan for additional travel time and to use alternative routes. Interchange ramps are closed to all hauling units.
EXPECT: Reconstruction activities; Width Restriction of 14 feet; Single Lane Closures; Flaggers.
I-90 - Mile Marker 110.1 to 110.6
Bridges Over The Blackfoot River near Bonner, MT.
Excavation activities
**Westbound Loads over 16 feet in width are required to stage in the signed staging area. At 6 a.m. MST, Monday through Thursday, the staged loads will be piloted through the construction.
**Eastbound Loads over 14 feet in width are required to stage in the signed staging area. At 7 a.m. MST, Monday through Thursday, the staged loads will be piloted through the construction.
***Any oversized load missing the designated piloting times will be required to wait until the next opening to be escorted through the project.***
For traffic control please contact Mountain West Holding: 406-490-8390
****32-J loads (those greater than 18 feet wide, 150 feet long, or 17 feet high) must contact the Prime Contractor at (406) 490-8390 Monday - Friday, 8:00 AM to 5:00 PM, before traveling to make special arrangements to be escorted through the project site on a case-by-case basis. 32- J carriers will be required to enter into a written agreement with the prime contractor to receive trip permits. All carriers may also consider use of an alternate route.
EXPECT: Bridge activities; Width Restriction of 14 feet; Reduced Speeds of 45 MPH; Single Lane Traffic.
I-90 - Mile Marker 134.8 to 150
Bearmouth East and West.
Mill/Fill in isolated sections, Seal and Cover Mainline. Seal and Cover Bearmouth Rest Area ramps and parking area, pavement markings and signing.
Currently, paving activities are taking place.
EXPECT: Sign installation activities.
I-90 - Mile Marker 140.8 to 141.2
2 Miles East of the Bearmouth Interchange.
Shoulder work and sign installation
EXPECT: Sign installation activities; Reduced Speeds of 35 MPH; Single Lane Traffic; Single Lane Closures; Flaggers.
I-90 - Mile Marker 227.5 to 241
Butte District Epoxy Striping.
Epoxy painting will be in progress at various times at the following locations.
(Helena Area)
Euclid Avenue
Prospect Avenue
Montana Avenue - Albertsons
South Montana Avenue
Lyndale - Montana Avenue
11th Avenue
Cedar Street
Custer Avenue
Helicopter East
Montana City to Blue Sky Hts.
Blue Sky Hts. to Jefferson City
EXPECT: Striping activities; Single Lane Traffic.
I-90 - Mile Marker 332 to 337
Yellowstone River - Livingston.
**A 12 foot width restriction is in place.
***Staging areas are available on each end of the project for loads between 12 and 18 feet in width. These loads will be escorted through the project site Monday through Thursday each week, between 8:00 AM and 9:00 AM Westbound and 9:00 AM to 10:00 AM for Eastbound traffic. For additional information call 406-490-8390.
**32- J loads (those greater than 18 feet wide, 150 feet long, or 17 feet high) must contact the Prime Contractor at (406) 490-8390 Monday-Friday, 8:00 AM to 5:00 PM, before traveling to make special arrangements to be escorted through the project site on a case-by-case basis. 32- J carriers will be required to enter into a written agreement with the prime contractor to receive trip permits. All carriers may also consider use of alternate routes.
EXPECT: Bridge activities; Width Restriction of 12 feet; Reduced Speeds of 45 MPH; Single Lane Traffic.
I-90 - Mile Marker 432.1 to 433
West Laurel Interchange.
Reconstruction of existing roadway and replace two structures on the West Laurel interchange. Both interstate ramps will be closed and traffic will need to use an alternate route. Width restrictions in effect until November 2018. Loads over 12 ft can be accommodated M-Th 6:30AM to 7:30 AM for westbound traffic and 5:30 AM to 6:30 AM for eastbound traffic. For accommodations please call Mtn. West Holding Co. at 406-671-5220, M-F 8AM-5PM.
EXPECT: Reconstruction activities; Width Restriction of 12 feet; Detour; Reduced Speeds varying from 45 to 55 MPH; Single Lane Traffic; Road Closure.
I-90 - Mile Marker 527 to 529
2 Miles North of Lodge Grass.
Single lane closure for retaining wall and culvert work.
EXPECT: Shoulder activities; Delays between 5 and 10 minutes; Reduced Speeds of 45 MPH; Single Lane Traffic; Single Lane Closures.
MT-1 - Mile Marker 8.1 to 8.1
Cedar Street - Anaconda.
*Milling and Paving in progress on Cedar Street. Traffic may be detoured to the nearest side street for easing impact to the traveling public.
*Installation of curb, gutter, and sidewalk on the east side of Cedar Street at the intersections is in progress. Pedestrian traffic is being detoured to the west side of Cedar Street.
*Expect delays of up to 10 minutes.
EXPECT: Sidewalk activities; Detour; Fresh Oil; Reduced Speeds of 10 MPH; Rough Roadway Surface; Single Lane Traffic; Single Lane Closures; Grooved Surface; Traffic Control by Signal Lights; Flaggers.
MT-1 - Mile Marker 29 to 29.5
About 8 miles south of Philipsburg.
Slope stabilization.
EXPECT: Rock activities; Delays up to 10 minutes; Reduced Speeds of 35 MPH; Pilot Cars; Single Lane Traffic; Traffic Control by Signal Lights.
MT-117 - Mile Marker 11.2 to 13
Nashua.
EXPECT: Shoulder activities; Reduced Speeds of 35 MPH.
MT-13 - Mile Marker 0 to 26
Circle to 26 Miles North.
EXPECT: Bridge activities; Reduced Speeds of 35 MPH; Single Lane Traffic.
MT-141 - Mile Marker 0 to 19.5
Avon North.
Crack sealing operations will consist of 2 mile sections at a time. Be prepared for short delays.
EXPECT: Crack sealing activities; Fresh Oil; Loose Gravel; Reduced Speeds of 35 MPH; Single Lane Traffic; Flaggers.
MT-141 - Mile Marker 19.6 to 32.7
MT-141: Nevada Lake Rd.
Crack seal operations in progress as weather permits.
EXPECT: Chip sealing activities; Delays up to 15 minutes; Fresh Oil; Reduced Speeds of 35 MPH; Single Lane Traffic.
MT-16 - Mile Marker 49.8 to 50
South of Sidney at the JCT of MT 16, MT 23, and MT 200.
The roundabout is open to single lane traffic. Watch for equipment working in the center of the roundabout. Watch for ditch workon MT 23 and MT 200 with trucks entering roadway.
EXPECT: Miscellaneous activities; Reduced Speeds of 35 MPH; Gravel Surface; Single Lane Traffic.
MT-19 - Mile Marker 54.7 to 66.6
Bohemain Corner South-JCT of US 191 and MT 19.
Weather permitting this chip seal will begin Monday June 18, 2018. Expect a width restriction of 14 feet.
EXPECT: Chip sealing activities; Width Restriction of 14 feet; Delays up to 15 minutes; Fresh Oil; Loose Gravel; Reduced Speeds of 35 MPH; Pilot Cars; Gravel Surface; Single Lane Traffic; Flaggers; Motorcycles Consider Alt Route.
MT-200 - Mile Marker 27.8 to 38.4
East and West of Richey.
Bore drill work will take place beginning Tuesday June 26th. Work will take place Tuesdays and Wednesdays 7:30 a.m. to 5 p.m. until approximately July 25th.
There will be no work taking place the week of July 2-6 due to the 4th of July holiday.
EXPECT: Miscellaneous activities; Single Lane Traffic; Flaggers.
MT-200 - Mile Marker 49.6 to 49.7
4 Miles Southeast of Ovando.
Bridge work will take place.
The eastbound lane will be open for single lane traffic in both directions and controlled by a signal light.
**Loads over 16 feet wide must use an alternate route.
EXPECT: Bridge activities; Width Restriction of 16 feet; Delays up to 15 minutes; Single Lane Traffic; Single Lane Closures; Traffic Control by Signal Lights.
MT-200 - Mile Marker 52.6 to 62.1
Sidney to Fairview.
Work will include overlay, widening and bridge deck rehabilitation.
EXPECT: Shoulder activities; Delays up to 15 minutes; Loose Gravel; Reduced Speeds of 35 MPH; Pilot Cars; Gravel Surface; Single Lane Traffic; Intersection Work.
MT-24 - Mile Marker 39.1 to 39.4
11 Miles South of Opheim.
There is a width restriction of 16 feet. A detour is in place.
EXPECT: Bridge activities; Width Restriction of 16 feet; Detour; Loose Gravel; Reduced Speeds of 35 MPH; Gravel Surface; Road Closure.
MT-35 - Mile Marker 40.3 to 48.1
From Creston North towards Kalispell.
Mill and Fill project. Expect night-time paving operations. Work will include: curb and gutter, sidewalk, guardrail, signing, striping, overlay, chip sealing, and crack sealing.
EXPECT: Overlay activities; Reduced Speeds varying from 25 to 35 MPH; Pilot Cars; Single Lane Closures; Flaggers.
MT-35 - Mile Marker 49.7 to 50
Helena Flats Intersection.
Utility work continues in preparation to add a 4-way traffic signal at the intersection of Helena Flats Road and MT Highway 35. This will have minimal traffic impacts. Work will include: chip sealing, sign installation, paving, grading, clearing and grubbing, and aligning a 4-way intersection. Estimated project completion date of June 15th, 2018.
EXPECT: Signal installation activities; Reduced Speeds of 35 MPH; Single Lane Closures; Flaggers.
MT-47 - Mile Marker 2.4 to 11.7
North of the Junction of MT-47 and I-90.
The Hardin North Road Project begins north of the Junction of MT-47 and I-90 and proceeds north on MT-47. Utility shifting and pipe work occurring. Please watch for workers in the roadway.
EXPECT: Reconstruction activities; Delays between 15 and 20 minutes; Reduced Speeds of 35 MPH; Motorcycles Consider Alt Route.
MT-55 - Mile Marker 7 to 12.1
South of Whitehall.
**Traffic on MT-55 south of Whitehall is now detouring onto Capp Lane during replacement of the bridge crossing Pipestone Creek.
**A 10 foot width restriction is in effect on MT-55 and the Capp Lane detour.
**A 10 ton weight restriction is in effect on the Capp Lane detour route.
**This restriction is expected to remain in effect until Fall of 2018.
EXPECT: Reconstruction activities; Width Restriction of 10 feet; Weight Restriction of 10 tons; Delays up to 15 minutes; Detour; Loose Gravel; Reduced Speeds of 35 MPH; Pilot Cars; Gravel Surface; Single Lane Traffic; Road Closure; Traffic Control by Signal Lights; Flaggers; Motorcycles Consider Alt Route.
MT-78 - Mile Marker 43.5 to 43.5
Shane Creek Road, Columbus MT.
Seal and cover operations will begin June 18, 2018. Expect single lane traffic controlled by signals, flaggers, and pilot cars.
EXPECT: Chip sealing activities; Delays up to 15 minutes; Pilot Cars; Single Lane Traffic; Traffic Control by Signal Lights; Flaggers.
MT-84/NORRIS ROAD - Mile Marker 21.2 to 29
Project begins 8 miles west of Four Corners and continues east to the Junction of Four Corners and Huffine (US-191)..
EXPECT: Chip sealing activities; Delays between 15 and 20 minutes; Fresh Oil; Loose Gravel; Reduced Speeds of 35 MPH; Pilot Cars; Gravel Surface; Single Lane Traffic; Flaggers; Motorcycles Consider Alt Route.
MT-85 - Mile Marker 3.4 to 6
Belgrade South.
*Reconstruction activities continue with special borrow and crushed aggregate placement, and storm drain and culvert installation.
**When construction operations are NOT taking place, traffic will still be reduced to two lanes at the intersections of Gallatin Heights Drive, Valley Center Road, Cameron Bridge Road and Frank Road.
***A 12 foot width restriction is in place.
**Contact Mountain West Traffic Control; 406-599-7122 to make arrangements to bring wide loads through.
EXPECT: Reconstruction activities; Width Restriction of 12 feet; Delays between 10 and 15 minutes; Reduced Speeds of 35 MPH; Gravel Surface; Single Lane Traffic; Intersection Work; Traffic Control by Signal Lights; Flaggers; Motorcycles Consider Alt Route.
MT-86 - Mile Marker .9 to 2.1
Rouse-Oak / Story Mill - Bozeman.
*Top soil placement and sidewalk installation in progress from Birdie Drive to Story Mill Road.
**An 11 foot width restriction is in effect.
FOR WIDE LOAD INFORMATION CALL - 406-490-8390
EXPECT: Reconstruction activities; Width Restriction of 11 feet; Delays up to 15 minutes; Reduced Speeds of 25 MPH; Pilot Cars; Single Lane Traffic; Traffic Control by Signal Lights; Flaggers.
MT-86 - Mile Marker 6.7 to 9
Guardrail Northeast of Bozeman.
*Paving work in progress.
**There is an 11 foot width restriction in place.
EXPECT: Paving activities; Width Restriction of 11 feet; Reduced Speeds of 35 MPH; Single Lane Traffic; Traffic Control by Signal Lights.
S-209 - Mile Marker 4.4 to 4.6
Swan River - 5 Miles East of Bigfork.
Bridge Replacement Project continues. The new detour is expected to open the week of May 21st with a 12 foot WIDTH RESTRICTION and reduced speeds. Bridge work will consist of Chip Sealing, Guardrail and Sign installation, Paving, Striping, and Seeding. Estimated completion date is September 2018.
EXPECT: Bridge activities; Width Restriction of 12 feet; Detour; Reduced Speeds of 35 MPH; Flaggers.
S-221 - Mile Marker 12 to 12
HIGHWAY BETWEEN CHOTEAU AND DUTTON MM 12.
CULVERT WORK
EXPECT: Miscellaneous activities.
S-227 - Mile Marker 8.5 to 13.4
1 mile before Stockett to 5 miles south.
Asphalt milling operations began on June 4th starting five miles south of Stockett. Paving operations to begin June 8th.
EXPECT: Milling activities; Delays up to 10 minutes; Reduced Speeds of 35 MPH; Pilot Cars; Single Lane Traffic; Single Lane Closures; Grooved Surface; Flaggers.
S-263/MULLAN ROAD - Mile Marker 5.8 to 10.1
MISSOULA, MULLAN RD..
STRIPING WORK ALSO IN PROGRESS
EXPECT: Chip sealing activities; Width Restriction of 12 feet; Delays up to 15 minutes; Fresh Oil; Loose Gravel; Gravel Surface; Single Lane Traffic; Flaggers.
S-284 - Mile Marker 12.5 to 16
Helena: Between E Shore Drive (MP 12.5) and Lewis and Clark County Line (MP 16.0).
There will be intermittent single lane closures and traffic will be controlled by pilot car or flaggers. Contractors will be working on underseal treatment, isolation lift, PMS overlay, guardrail, bridge rail, seal and cover and pavement marking. Motorcycles are urged to consider an alternate route due to loose chips on the roadway.
EXPECT: Chip sealing activities; Delays up to 15 minutes; Fresh Oil; Loose Gravel; Reduced Speeds of 35 MPH; Pilot Cars; Single Lane Closures; Flaggers; Motorcycles Consider Alt Route.
S-288 - Mile Marker 6.1 to 16
Jct MT 84 to Jct S-347 (S-288).
*Alternating single lane traffic at milepost 11.6.
*Chip sealing is scheduled to begin on June 12, 2018.
*Bridge repair work scheduled to begin on June 12, 2018.
EXPECT: Chip sealing activities; Delays up to 15 minutes; Fresh Oil; Loose Gravel; Reduced Speeds of 35 MPH; Pilot Cars; Gravel Surface; Traffic Control by Signal Lights; Flaggers; Motorcycles Consider Alt Route.
S-311 - Mile Marker 3 to 9.2
Hysham West.
Please watch for workers on the road.
EXPECT: Reconstruction activities; Width Restriction of 14 feet; Reduced Speeds of 35 MPH; Single Lane Traffic; Single Lane Closures; Flaggers.
S-330 - Mile Marker 36.8 to 36.9
Cascade: three different segments 1) 4th Ave N from 4th St N to 2nd St N; 2) 4th Ave N and 1st St N to multi-use path; 3) 3rd St from 2nd Ave S to Central Ave.
Installation of sidewalks, curb and gutter, and ADA curb ramps.
EXPECT: Miscellaneous activities; Delays up to 15 minutes; Single Lane Traffic; Flaggers.
S-330 - Mile Marker 36.8 to 36.9
Cascade: Central Ave from 1st St N west to the Missouri River.
Work consists of mill, overlay, sidewalk and curb, curb and gutter, seal and cover along with signing.
EXPECT: Miscellaneous activities; Delays up to 15 minutes; Single Lane Traffic; Flaggers.
S-366 - Mile Marker 13 to 28.6
I-15 EXIT 345 TO 13 MILES EAST ON S-366.
**updated**Contracted fog sealing to begin on Friday, June 15. Motorcycles are urged to consider another route. Please use caution in work zones.
EXPECT: Chip sealing activities; Delays up to 15 minutes; Fresh Oil; Loose Gravel; Reduced Speeds of 35 MPH; Pilot Cars; Gravel Surface; Single Lane Traffic; Single Lane Closures; Flaggers; Motorcycles Consider Alt Route.
S-464 - Mile Marker 26 to 33.6
DUCK LAKE.
Work operations will be off the roadway but there will be workers and equipment frequently crossing the roadway.
EXPECT: Fencing activities; Reduced Speeds of 55 MPH.
S-548 - Mile Marker 4.6 to 5.8
West Reserve Drive - Stillwater River Bridge to Whitefish River Bridge.
Overlay and Chip Seal of West Reserve Drive. Milling and Paving will begin on Monday, June 11th. Expect day and night work throughout the duration of this project.
EXPECT: Overlay activities; Reduced Speeds varying from 25 to 35 MPH; Pilot Cars; Single Lane Closures; Flaggers.
S-574 - Mile Marker 0 to 10.9
Huson - East Secondary Highway Route 574.
Complete road reconstruction and utility work in progress. Heavy equipment and road workers present during daytime hours Monday through Friday. Placing Pipes across roads at various locations. Gravel travel surfaces. Anticipate multiple work zones through the 11 mile project.
*Multi-Use path is now closed throughout the entire project until further notice. The Frontage Road is not recommended as an alternative for pedestrians and cyclists due to heavy equipment and haul trucks operating on and along the roadside.
EXPECT: Reconstruction activities; Delays up to 5 minutes; Reduced Speeds varying from 35 to 50 MPH; Single Lane Traffic; Traffic Control by Signal Lights; Flaggers.
US-12 - Mile Marker 0 to 40.2
Garrison to Helena on US-12 & Montana City roundabout south 2 miles on S-282.
Starting June 19th, the contractor will begin milling rumble strips starting at Garrison and working towards Helena. Work is expected to take around 2.5 days with the Montana City area to be done on the last day. The grinding, fog seal, painting, signs and electrical work will take place starting Wednesday, September 5th.
EXPECT: Rumble strip activities; Delays up to 15 minutes; Fresh Oil; Reduced Speeds of 35 MPH; Pilot Cars; Single Lane Traffic; Flaggers.
US-12 - Mile Marker 44.3 to 44.4
Intersection of 11th and Montana Ave..
Work being performed by the city of Helena to replace a storm drain will be in progress during the evening from 7:00 p.m to 6:00 a.m.
EXPECT: Miscellaneous activities; Detour; Single Lane Traffic; Single Lane Closures.
US-12 - Mile Marker 159.8 to 165.6
Nine miles west of Roundup.
Beginning Sunday June 17th through Friday June 22nd ROAD WILL BE CLOSED at mile marker 161.4, approximately 8 miles west of Roundup from 9pm to 6am each night. No traffic will be allowed to pass during this time frame. Alternate routes will be required. Expect a width restriction of 13 feet.
EXPECT: Reconstruction activities; Width Restriction of 13 feet; Reduced Speeds of 25 MPH; Pilot Cars; Gravel Surface; Single Lane Traffic; Single Lane Closures; Road Closure; Traffic Control by Signal Lights; Flaggers.
US-2/9TH STREET WEST - Mile Marker 134.2 to 137.4
COLUMBIA FALLS.
Night work will continue for the remainder of the week. Day-time Paving operations will begin next week. This will be followed by chip sealing in June.
EXPECT: Paving activities; Reduced Speeds of 35 MPH; Single Lane Closures.
US-2 - Mile Marker 141.5 to 142.6
South Fork of Flathead River Bridge - HUNGRY HORSE.
Dirt work in progress. Expect occasional night work.
Use of Forest Service roads within the project boundaries has been restricted or prohibited for safety purposes. Details can be obtained from the Hungry Horse Ranger District of the Flathead National Forest. REF: Order # D06-138-S-17.
EXPECT: Bridge activities; Delays between 10 and 15 minutes; Reduced Speeds varying from 35 to 45 MPH; Flaggers.
US-2 - Mile Marker 155.8 to 155.8
2 Miles East of West Glacier Park Entrance.
Crews will be working on slope stabilization in this area.
EXPECT: Miscellaneous activities; Reduced Speeds of 35 MPH; Pilot Cars; Single Lane Traffic; Traffic Control by Signal Lights; Flaggers.
US-2 - Mile Marker 299.8 to 308
Galata East and West between Shelby and Chester.
Reconstruction work in progress. Loads over 14-feet wide could experience substantial delays. Please consider an alternate route. Motorcycles and bicyclists should also consider an alternate route.
EXPECT: Reconstruction activities; Delays up to 15 minutes; Loose Gravel; Reduced Speeds of 35 MPH; Pilot Cars; Gravel Surface; Single Lane Traffic; Traffic Control by Signal Lights; Motorcycles Consider Alt Route.
US-2 - Mile Marker 555 to 556
Nashua.
EXPECT: Miscellaneous activities; Reduced Speeds of 35 MPH; Flaggers.
US-212 - Mile Marker 69.6 to 76.9
7 Miles East of Ashland to 14 Miles East of Ashland.
There is a width restriction of 16 feet. For wide loads needing to travel through please contact Cody with Wickens Construction at (406) 350-0671 at least 24 hours in advance of travel to make arrangements.
EXPECT: Reconstruction activities; Width Restriction of 16 feet; Delays up to 15 minutes; Detour; Loose Gravel; Reduced Speeds of 35 MPH; Pilot Cars; Rough Roadway Surface; Single Lane Traffic; Traffic Control by Signal Lights; Motorcycles Consider Alt Route.
US-310 - Mile Marker 38.2 to 39.4
Billings South Safety Improvements.
Curve signing, delineation panels and advanced warning beacon installation. Please watch for workers in the roadway.
EXPECT: Miscellaneous activities; Reduced Speeds of 35 MPH; Single Lane Closures; Flaggers.
US-310 - Mile Marker 42.5 to 52.5
South of Laurel at intersections of Whitehorse South & North Roads and Whitehorse Ranch Road.
Heavy equipment traffic at the intersections of Whitehorse South Road & Whitehorse North Road.
EXPECT: Miscellaneous activities; Reduced Speeds of 25 MPH; Intersection Work.
US-87 - Mile Marker 33.8 to 45.1
Grass Range South.
Width restriction of 13 feet is in affect during working hours. Contact Mountain West Holding for wide load information (406)671-5232
EXPECT: Milling activities; Width Restriction of 13 feet; Delays up to 15 minutes; Fresh Oil; Reduced Speeds of 35 MPH; Pilot Cars; Single Lane Traffic; Single Lane Closures; Grooved Surface; Traffic Control by Signal Lights; Flaggers; Motorcycles Consider Alt Route.
US-87 - Mile Marker 57.8 to 62.7
Hobson East.
Width restriction of 16 feet during daylight construction hours.
EXPECT: Reconstruction activities; Width Restriction of 16 feet; Delays up to 15 minutes; Loose Gravel; Reduced Speeds of 45 MPH; Pilot Cars; Gravel Surface; Rough Roadway Surface; Single Lane Traffic; Traffic Control by Signal Lights; Flaggers; Motorcycles Consider Alt Route.
US-89 - Mile Marker 5.6 to 9.9
East of Kiowa.
Pavement patching starts June 13th. Rumble stripping expected to start June 14th.
EXPECT: Rumble strip activities; Delays up to 15 minutes; Reduced Speeds of 35 MPH; Pilot Cars; Single Lane Traffic; Flaggers.
US-89 - Mile Marker 9.9 to 14.4
Two miles east of Kiowa Junction to two miles north of Kiowa Junction.
Reconstruction work in progress.
Project WEB Site: 1
EXPECT: Reconstruction activities; Delays up to 20 minutes; Loose Gravel; Reduced Speeds of 35 MPH; Pilot Cars; Single Lane Traffic; Single Lane Closures; Grooved Surface; Flaggers; Motorcycles Consider Alt Route.
US-89 - Mile Marker 38 to 54
Monarch Canyon to Neihart.
Seal and cover operations from 7:00 am to 7:00 pm Wednesday, Thursday, and Friday (June 6th, 7th and 8th).
EXPECT: Chip sealing activities; Delays up to 15 minutes; Fresh Oil; Loose Gravel; Reduced Speeds of 35 MPH; Pilot Cars; Gravel Surface; Single Lane Traffic; Single Lane Closures.
US-89 - Mile Marker 52.5 to 52.5
Sidewalk Improvements at Various Locations in Bozeman and Livingston.
*Demolition work, concrete sidewalk, and ADA ramp replacement continues in Bozeman.
*Minor cleanup work remains in Livingston.
*Streets will be closed two blocks at a time.
Main St - Bozeman , Yerger Dr to West Babcock St
N 7th Ave - Bozeman, Aspen St to Wheat St./ Nikles Dr
N 19th Ave - Bozeman, Commerce Way to 22nd Ave
Geyser St.- Livingston, between Park St. to H St.
Park St.- Livingston, between Merrill Ln. to I St.
EXPECT: Sidewalk activities; Single Lane Closures; Road Closure; Intersection Work.
US-93 - Mile Marker 64.4 to 65
Northwest of Polson.
Crews will be working to widen the roadway in this area to accommodate for the addition of turn lanes. Work will include chip sealing, overlay, guardrail, sign installation, striping, shoulder activities, adding rumble strips, seeding, fencing, and culvert installation. Work should last approximately 4-6 weeks.
EXPECT: Reconstruction activities; Delays between 10 and 15 minutes; Reduced Speeds varying from 25 to 35 MPH; Single Lane Traffic; Flaggers.
OVERLOOK DRIVE - Mile Marker 0 to .3
Great Falls: Overlook Drive Pedestrian Path from 10th Avenue South to just past the Visitors Center.
Project work includes new curb, drainage structures and pedestrian path. A detour will be in place for northbound traffic between May 7th and June 6th. Flagging operations will be in place daily from June 7th to June 13th.
EXPECT: Miscellaneous activities; Detour; Single Lane Traffic; Single Lane Closures; Road Closure; Flaggers.
NORTH FORK ROAD - Mile Marker 0 to 1
MILK RIVER 4 MILES WEST OF ZURICH.
Bridge is out. Local road/route 308 North Fork Road will be closed until new bridge is completed.
EXPECT: Bridge activities; Road Closure.
DIVISION ST - Mile Marker .1 to .5
Billings Downtown Area- Division Street from 1st Ave N to Grand and 6th Ave. N from 27th Street to 32nd Street.
Work will begin June 5th with the demolition and replacement of sidewalk corners. Following weeks will include milling and paving the streets.
EXPECT: Sidewalk activities; Reduced Speeds of 25 MPH; Single Lane Traffic; Single Lane Closures; Intersection Work; Flaggers.
I-90 FRONTAGE ROAD - Mile Marker .5 to .7
East of Laurel on Frontage Road near BBWA Canal.
Installation of optional terminal sections and relocation of a farm field approach. Please watch for workers in the roadway.
EXPECT: Miscellaneous activities; Reduced Speeds of 35 MPH; Single Lane Closures; Flaggers.
ORANGE ST - Mile Marker 1 to 2.2
Various Intersections throughout Missoula.
ADA upgrades on the following intersections
Orange & Broadway
Orange & N 2nd st
Orange & Alder
Orange & Spruce
Orange & Pine
*Pedestrian detours will be placed as needed
EXPECT: Sidewalk activities; Single Lane Closures; Intersection Work.
DOC'S ROAD - Mile Marker 1 to 6
Doc's Road.
Chip seal activities will begin on June 8th, 2018. Sweeping and cleanup is scheduled for June 9th, 2018 followed by striping. Be prepared for short delays.
EXPECT: Chip sealing activities; Reduced Speeds of 35 MPH; Pilot Cars; Single Lane Traffic.
FOX FARM ROAD - Mile Marker 1.2 to 3.1
Fox Farm Road between East Fiesta and Dick Road.
Reconstruction work in progress between mile marker 2.5 and 3.05. Southbound detour in place from 45th Avenue South to Flood Road with access back to Fox Farm Road via Dick Road. Northbound detour to flood Road via Dick Road.
EXPECT: Reconstruction activities; Detour; Reduced Speeds of 25 MPH; Gravel Surface; Road Closure; Intersection Work; Motorcycles Consider Alt Route.
RUSSELL STREET - Mile Marker 2.5 to 3
Russell Street Missoula.
Russell Street Traffic will have a slight detour around the Milwaukee Trail. The detour will be in place from Friday May 25th through the end of August.
Traffic is two way without a center turn lane.
Wyoming Street east of Russell Street to Inez Street is anticipated to be closed through the end of June.
Dakota Street is closed at the intersection with Russell Street through November 2018.
River Road is anticipated to be closed Tuesday May 29th through the end of June from Russell Street to Mobil City Trailer Park. Traffic will need to head west on River Road then South on N. Curtis Street then East on Wyoming Street to access Russell Street.
Milwaukee Trail will be closed through November 2018 from Catlin Street to Prince Street. Detour will be in place.
North Riverfront Trail will be closed from California Street to around 200 feet west of Catlin through August 2019.
Project WEB Site: Russell
EXPECT: Reconstruction activities; Reduced Speeds of 25 MPH.
I-15 CONRAD OVERPASS, EXIT 339 - Mile Marker 5 to 5
I-15 Conrad Overpass, Exit 339.
Bridge preservation work in progress. Width restriction of 10-feet is in place on the overpass. Oversize loads should use exit 335 from I-15 to enter Conrad.
EXPECT: Bridge activities; Width Restriction of 10 feet; Reduced Speeds of 35 MPH; Single Lane Traffic; Single Lane Closures; Road Closure; Intersection Work.
OLD US 91 - Mile Marker 34 to 36
5 miles south of Cascade.
Road is closed due to slide. Traffic traveling on Old US-91 can bypass the slide by using the South Cascade Interchange (Exit 254) and the Tintinger Interchange (Exit 250)
EXPECT: Rock activities; Detour; Road Closure.

Completed Construction Projects

I-15 - Mile Marker 218 to 220 (Completed)
8 Miles South of Wolf Creek.
I-15 - Mile Marker 218 to 220 (Completed)
work zone starts one mile south of Spring Creek Interchange (exit 219).
I-15 - Mile Marker 224.5 to 225.5 (Completed)
3 Miles North of Lyons Creek Parking Area.
I-15 - Mile Marker 240 to 242 (Completed)
Dearborn River - Approx 6 Miles N of Craig.
I-15 - Mile Marker 240 to 241 (Completed)
Exit 240 Dearborn Interchange.
I-90 - Mile Marker 23 to 28 (Completed)
Drexel - East and West.
MT-200 - Mile Marker 7.5 to 9 (Completed)
Rainbow Bend east of Bonner.
MT-200 - Mile Marker 52.2 to 52.2 (Completed)
Browns Lake Area - Approx 16 Miles West of Lincoln.
MT-200 - Mile Marker 67.4 to 67.4 (Completed)
3 Miles West of the Lewis & Clark and Powell County Line.
This project is complete.
MT-200 - Mile Marker 82.9 to 88.2 (Completed)
From Junction with S-279 east six miles to Rogers Pass.
Project complete.
MT-200 - Mile Marker 102.4 to 102.4 (Completed)
7 miles west of Bowman's Corner.
MT-81 - Mile Marker 33.9 to 42.4 (Completed)
10 miles north of Lewistown.
Scrub Seal project is complete
S-220 - Mile Marker 15 to 16 (Completed)
15 Miles North of Choteau.
Intermittent lane closures for machine patching.
S-222 - Mile Marker 0 to 3.5 (Completed)
Hwy-222, South of Dillon.
S-411/SPRINGHILL ROAD - Mile Marker 0 to 6.2 (Completed)
Bozeman from the Junction with S-205 to 6 miles north..
Weather permitting.
S-430/CANYON FERRY RD - Mile Marker 2 to 3.1 (Completed)
Helena: Canyon Ferry Rd from Wylie Dr to Valley Dr.
Project complete
US-12 - Mile Marker 47.6 to 48.3 (Completed)
East Helena.
US-87 - Mile Marker 43.4 to 52 (Completed)
Bridge near Fort Benton.
Seal, cover, and striping are yet to be finished.
CEDAR ST - Mile Marker 1.1 to 2.1 (Completed)
Helena: Cedar St from Montana Ave to Washington St.
Project Complete
CUSTER AVENUE - Mile Marker 1.5 to 2.5 (Completed)
Helena: from Custer Avenue to Montana Avenue.
Project complete.
CASCADE SOUTH FRONTAGE ROAD - Mile Marker 31 to 38.8 (Completed)
Frontage Road (Old US 91) between Hardy Creek and Cascade.
Crack sealing operations are completed. Chip seal to occur later in the summer.

Inactive Construction Projects

I-15 - Mile Marker 150.9 to 157.7 (Inactive)
Bernice to Basin.
I-15 - Mile Marker 189.9 to 194 (Inactive)
Lewis and Clark/Jefferson County Line north to just north of Custer Avenue.
** This project is currently inactive.
I-15 - Mile Marker 205 to 209 (Inactive)
Bottom of North Hill - Helena.
This project is currently inactive.
***There are no restrictions at this time.
I-15 - Mile Marker 217.5 to 222 (Inactive)
5 Miles South of Wolf Creek Interchange to Sieben Interchange (Exit 216).
Traffic has returned to normal, while inactive.
I-15 - Mile Marker 282 to 286 (Inactive)
Emerson Jct to Manchester.
This project is inactive until spring 2018.
I-90 - Mile Marker 22 to 23 (Inactive)
Missoula Horizontal Curves.
No work at this time.
Signing crews plan to install overhead signs.
I-90 - Mile Marker 104.5 to 104.9 (Inactive)
Orange Street Interchange.
Currently inactive.
I-90 - Mile Marker 118.6 to 118.6 (Inactive)
3 MILES WEST OF CLINTON INTERCHANGE.
This project is currently inactive.
I-90 - Mile Marker 240.1 to 249.2 (Inactive)
Pipestone - Whitehall.
*Starting July 9th, 2018, chip seal work will be in progress weather permitting.
I-90 - Mile Marker 450 to 453 (Inactive)
Billings Area-Yellowstone River Bridge.
No work at this time.
.
I-90 - Mile Marker 526.2 to 529.1 (Inactive)
Eastbound lanes, Lodge Grass Area.
No work at this time
I-94 - Mile Marker 217.9 to 223.8 (Inactive)
East of Glendive-East.
Work will be suspended for the winter.
I-94 - Mile Marker 231.4 to 243.7 (Inactive)
WIBAUX- EAST AND WEST.
Work will be suspended for the winter
MT-1 - Mile Marker 23.5 to 23.5 (Inactive)
West Valley - Georgetown.
Project is inactive until chip seal in the spring of 2018.
MT-135 - Mile Marker 0 to 1 (Inactive)
4-Way Stop in St Regis.
Signing, delineation and minor excavation along the shoulder of the road.
MT-2 - Mile Marker 83.3 to 86.5 (Inactive)
Harrison Ave. - South.
MT-200 - Mile Marker 102 to 106.2 (Inactive)
Montana 200 / National Highway Route N-24 in Lewis and Clark County.
No work scheduled, waiting on weather to allow seeding.
MT-200 - Mile Marker 173.5 to 220 (Inactive)
Beginning at Moseby to 7 Miles East of Jordan.
MT-23 - Mile Marker 0 to 2.8 (Inactive)
Sidney heading East.
MT-24 - Mile Marker 8 to 60 (Inactive)
8 Miles North of Glasgow to the Canadian Border.
MT-287 - Mile Marker 1.2 to 1.2 (Inactive)
1.2 MILES SOUTHWEST OF ENNIS..
DETOURS WILL BE POSTED.
MT-39 - Mile Marker 0 to 51 (Inactive)
Beginning at Lame Deer to Colstrip Interchange.
MT-80 - Mile Marker 4.1 to 14.7 (Inactive)
US 80 Southeast of Fort Benton.
Project will proceed summer of 2018.
RT-201 - Mile Marker 37.8 to 68.8 (Inactive)
Fairview heading West towards Girard.
S-210 - Mile Marker 1 to 1.5 (Inactive)
East of Bonner.
S-221 - Mile Marker 6.1 to 14.5 (Inactive)
S-221 between Choteau and Dutton.
Paving operations are complete. Chip seal operations to occur end of July or first of August.
S-238 - Mile Marker .4 to 7.2 (Inactive)
Lewistown Southeast - Spring Creek Road / Secondary 238.
All restrictions have been removed while project is INACTIVE.
S-246 - Mile Marker 0 to 11 (Inactive)
Glasgow.
S-278 - Mile Marker 19.7 to 30 (Inactive)
Southwest of Dillon.
Project inactive until milling and paving operations begin.
S-279 - Mile Marker 1.8 to 2.4 (Inactive)
Intersection of Lincoln Road and Green Meadow Road.
Project inactvie till final striping and seeding
S-279 - Mile Marker 8.6 to 22 (Inactive)
S-279 from Birdseye Road to Stemple Pass.
Project inactive till final striping and seeding
S-292 - Mile Marker 0 to 3.2 (Inactive)
From Reserve Dr North.
Paving and Striping has been completed for this project. Crews will begin chip sealing this section of Whitefish Stage in early June.
S-297 - Mile Marker 20.7 to 25.7 (Inactive)
Careless Creek North.
Work is suspended until Spring of 2018.
S-314 - Mile Marker 25.4 to 31.8 (Inactive)
North of Decker.
Project is complete pending punch list items.
S-336 - Mile Marker 0 to 7.8 (Inactive)
15 miles north of Baker.
S-345/COTTONWOOD AND STUCKY INTERSEC - Mile Marker .8 to 1.2 (Inactive)
Intersection of Cottonwood and Stucky Roads.
S-379/16TH ROAD NE - Mile Marker 0 to 14.1 (Inactive)
Dutton - East 14 Miles.
Punch list items only-no work scheduled.
S-409/WHITLASH ROAD - Mile Marker 0 to 6 (Inactive)
Chester to 6 miles north (Whitlash Road) Detour Tiber Road.
Project inactive until final seal and cover in 2018
S-426 - Mile Marker 0 to .5 (Inactive)
Moccasin Railroad Crossing.
Inactive for winter.
S-430/CANYON FERRY DRIVE - Mile Marker .5 to 1 (Inactive)
.5 miles past the York Road intersection.
Work is temporarily suspended.
S-432 - Mile Marker 27.2 to 46.5 (Inactive)
Crack Sealing Project on South Rudyard Road.
Crack sealing--On hold due to weather.
S-471 - Mile Marker 0 to 21 (Inactive)
Missoula Horizontal Curves.
Work is currently suspended.
S-489 - Mile Marker 0 to 18 (Inactive)
Beginning at the intersection of MT-59 and S-489 to Kinsey.
US-12 - Mile Marker 84 to 95 (Inactive)
Baker to the North Dakota Line.
US-12 - Mile Marker 94 to 94 (Inactive)
MADISON STREET BRIDGE REHAB.
*This project is currently inactive.
US-12 - Mile Marker 121.7 to 184 (Inactive)
Bank Stabilization East of Roundup.
Contracted work is complete, project is INACTIVE while punch list items are addressed.
US-191 - Mile Marker 35 to 42.8 (Inactive)
Roy East.
US-191 - Mile Marker 118.1 to 156.9 (Inactive)
Malta.
US-2/YAAK HILL - Mile Marker 5.5 to 5.8 (Inactive)
East of Idaho State Line.
This project is in winter shutdown.
US-2 - Mile Marker 150.1 to 150.6 (Inactive)
Junction with Lake Five Road, East of Coram.
Waiting for Epoxy Striping to be scheduled.
US-2 - Mile Marker 158.7 to 158.7 (Inactive)
East of WEST GLACIER.
Slope stabilization work has been completed. This project will be inactive until further notice. Guardrail and pipe work will be completed when project becomes active.
US-2 - Mile Marker 223.7 to 223.7 (Inactive)
Mile Marker 223.7 East of Browning at Junction of US-89.
Project is substantially complete.
US-2 - Mile Marker 471 to 540 (Inactive)
Glasgow to Malta.
US-212 - Mile Marker 22.2 to 38.6 (Inactive)
Bighorn (milepost 22.2) to Rosebud County (milepost 62.8).
No work at this time.
US-212 - Mile Marker 41.9 to 42.3 (Inactive)
Intersection of US 212 and MT 39.
US-212 - Mile Marker 61 to 103 (Inactive)
Beginning 3 miles West of Broadus towards Ashland.
US-87 - Mile Marker 7.1 to 21 (Inactive)
US-87 Judith Basin County Line to Geyser.
Final epoxy paint striping tentatively scheduled for July 16th. Roadway is open.
US-87/US 191 / MT 200 - Mile Marker 79 to 81.1 (Inactive)
Lewistown West - Overpass.
Inactive for winter
US-87/LEWISTOWN WALKING PATHS - Mile Marker 80 to 82.5 (Inactive)
City Loop Walking Paths - Abandoned Railroad (C).
Restrictions have been removed while project is INACTIVE.
US-87/US 191 / MT 200 - Mile Marker 81.4 to 81.5 (Inactive)
Lewistown West - Sidewalks (D).
Sidewalk work from 15th street to 13th street is INACTIVE.
US-87/US 191 / MT 200 - Mile Marker 81.5 to 82.8 (Inactive)
Lewistown Downtown Sidewalks (B).
All restrictions are removed while project is INACTIVE.
US-89 - Mile Marker .1 to 7 (Inactive)
Mission Interchange - North.
US-89 - Mile Marker 14 to 14 (Inactive)
Yankee Jim Canyon - North.
Project inactive until spring 2018.
US-89 - Mile Marker 49.6 to 55.4 (Inactive)
Bynum south six miles.
No construction activities.
US-93 - Mile Marker 4 to 18.5 (Inactive)
HWY 93 NORTH OF MISSOULA.
Construction crews are preparing the road for seal & cover work to begin after July 9th. Week of June 11th there will be milling, paving, and rumble strip work from mile post 9 through 11. Other intermittent work zones are possible throughout the entire project.
1ST AVE SOUTH - Mile Marker 0 to 0 (Inactive)
Billings-1st Ave South from Broadway to State Ave also State Ave from 1st Ave South to Underpass Ave, Underpass Ave from State to Laurel Road, Laurel Road from Underpass to King Ave West..
Project is complete pending punchlist items and cleanup.
1ST AVE NORTH - Mile Marker 0 to 0 (Inactive)
Billings-1st Ave North 25th Street to Division Street also Montana Ave and North 28th Street to North 30th Street.
Punch list items and clean up are pending.
MONTANA AVENUE - Mile Marker 1.4 to 4.1 (Inactive)
Montana Ave. from Sierra to Custer.
Chip seal activities will begin on June 6th, 2018. Sweeping and cleanup is scheduled for June 8th, 2018 followed by striping. Be prepared for short delays.
SOUTH PARK AVENUE - Mile Marker 2 to 2.4 (Inactive)
Helena: South Park Avenue from Broadway Street to Cruse Street.
Project inactive until final striping and seeding