October 23-27, 2023

Fall weather has set in, and the Montana Department of Transportation (MDT) and Riverside Contracting Inc. are concluding work on the MT 64 TIGER Grant project for 2023. Here’s what you can expect for the week of October 23.

Landscaping work is finished for the year. Signage installation is scheduled for this week, and minimal traffic impacts are expected while this work is occurring. Outstanding irrigation activities will be conducted next spring.

Signal activation at Little Coyote Road is anticipated for October 25, but is dependent upon Northwestern Energy’s completion of the power service.

Project segments completed this year:

  • Construction of a left-turn lane at Big Sky Resort Road.
  • Construction of left-turn lanes at Andesite Road and Big Pine Drive.
  • Paved shared-use path along MT 64 from Big Pine Drive to Andesite Road.
  • Construction of a left-turn lane and associated improvements at Huntley Drive.
  • Construction of a pedestrian bridge adjacent to the Big Sky Community Park.
  • Installation of a traffic signal and left and right-turn lanes at Little Coyote Road.
  • Construction of a left-turn lane at Meadow Village Drive.
  • Construction of a pedestrian tunnel under MT 64 west of Little Coyote Drive.
  • Signage upgrades.

Segments to be completed in 2024

  • Improvements at US Highway 191 (US 191) including the elimination of gravel shoulder parking by extending curb and gutter, installation of paved bus pull-outs, and installation of pull-outs for wildlife viewing.
  • Paving through the pedestrian tunnel.
  • Kircher Park Trail repairs.
  • Seal and cover (chip seal) of the project area.
  • Permanent roadway striping.

Construction on the pedestrian tunnel is substantially complete. The trail is paved up to both tunnel entrances. The remaining section through the tunnel will be paved in 2024. There is an uneven surface at both ends and concrete joints throughout the tunnel that could be a tripping hazard. Tunnel lighting is expected to be turned on in conjunction with the Little Coyote Road signal activation. Pedestrians using the path and tunnel are encouraged to use caution.

Kircher Park Trail is closed while the MT 64 TIGER Grant project team evaluates needed repairs. A survey of the area has occurred, and project team members are working closely with the Big Sky Community Organization to create a repair plan. The project team anticipates repairs will be completed as early as next spring, weather and other factors permitting. The trail will remain closed until repairs are completed.

MDT, Gallatin County, and project contractors are grateful for the community's patience and support during this project.

This will be the last weekly update this season. Updates will resume with construction activities in 2024.

Traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day from the project's main page.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

October 16-20, 2023

The Montana Department of Transportation (MDT) and Riverside Contracting Inc. continue work on the MT 64 TIGER Grant project. Here’s what you can expect for the week of October 16.

Signage installation and landscaping activities are ongoing. Crews will be planting vegetation throughout the weekend, as well as on Monday, October 16, as necessary. Landscaping is anticipated to be completed by the end of the week, weather permitting. Sign installation and landscaping will take place on the shoulder, and minimal traffic impacts are expected for these activities.

Final construction activities are taking place on the traffic signal at Little Coyote Road, which is now anticipated to be activated on October 25.

Temporary striping is complete, and crews will return in 2024 to complete a seal and cover (chip seal) and paint permanent roadway stripes.

Construction on the pedestrian tunnel is substantially complete. The trail is paved up to both tunnel entrances. The remaining section through the tunnel will be paved in 2024. There is an uneven surface at both ends and concrete joints throughout the tunnel that could be a tripping hazard. Tunnel lighting is expected to be turned on in conjunction with the Little Coyote Road signal activation. Pedestrians using the path and tunnel are encouraged to use caution.

Improvements near the intersection of Montana Highway 64 (MT 64) and US Highway 191 (US 191) will be completed during the 2024 construction season.

Kircher Park Trail is closed while the MT 64 TIGER Grant project team evaluates needed repairs. A survey of the area has occurred, and project team members are working closely with the Big Sky Community Organization to create a repair plan. The project team anticipates repairs will be completed as early as next spring, material availability and weather permitting. The trail will remain closed until repairs are completed.

MDT, Gallatin County, and project contractors are grateful for the community's patience and support during this project.

Weekly updates will continue to be provided throughout construction.

Traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day from the project's main page.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

October 9-13, 2023

The Montana Department of Transportation (MDT) and Riverside Contracting Inc. continue work on the MT 64 TIGER Grant project. Here’s what you can expect for the week of October 9.

Crews will be on-site Monday, October 9, to remove concrete barrier rail and install new guardrail. Drivers can expect reduced speeds and periodic lane closures throughout the project area while guardrail work occurs.

Signage installation and landscaping activities continue this week. This work will take place on the shoulder, and no lane closures are expected for these activities.

Final construction activities are taking place on the traffic signal at Little Coyote Road, which is anticipated to be activated on October 12.

Pedestrian rail installation on the shared-use path between Big Pine Drive and Andesite Road is anticipated to occur this week. Periodic trail closures may be necessary while the railing is installed.

Temporary striping is complete, and crews will return in 2024 to paint permanent roadway stripes.

Construction on the pedestrian tunnel is substantially complete. The trail is paved up to both tunnel entrances. The remaining section through the tunnel will be paved in 2024. There is an uneven surface at both ends and concrete joints throughout the tunnel that could be a tripping hazard. Pedestrians using the path and tunnel are encouraged to use caution.

Improvements near the intersection of Montana Highway 64 (MT 64) and US Highway 191 (US 191) will be completed during the 2024 construction season.

Kircher Park Trail is closed while the MT 64 TIGER Grant project team evaluates needed repairs. A survey of the area has occurred, and project team members are working closely with the Big Sky Community Organization to create a repair plan. The project team anticipates repairs will be completed as early as material availability and weather allows next spring. The trail will remain closed until repairs are completed.

MDT, Gallatin County, and project contractors are grateful for the community's patience and support during this project.

Weekly updates will continue to be provided throughout construction.

Traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day from the project's main page.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

October 2-6, 2023

The Montana Department of Transportation (MDT) and Riverside Contracting Inc. continue work on the MT 64 TIGER Grant project. Here’s what you can expect for the week of October 2.

Crews will be on site this week to remove old roadway markings and place remaining temporary roadway striping. Periodic lane closures are possible while this work occurs.

Signage installation will begin Tuesday, October 3, and landscaping activities will begin Wednesday, October 4. Work will take place on the shoulder, and no lane closures are expected. Guardrail installation is anticipated for later this month.

Construction on the pedestrian tunnel is substantially complete. The trail is paved up to both tunnel entrances. The remaining section through the tunnel will be paved in 2024. There is an uneven surface at both ends and concrete joints throughout the tunnel that could be a tripping hazard. Pedestrians using the path and tunnel are encouraged to use caution.

Final construction activities are taking place on the traffic signal at Little Coyote Road, which is anticipated to be activated on October 12.

Pedestrian rail installation on the shared-use path between Big Pine Drive and Andesite Road will begin this week. Periodic trail closures may be necessary while the railing is installed.

Improvements near the intersection of Montana Highway 64 (MT 64) and US Highway 191 (US 191) will be completed during the 2024 construction season.

Kircher Park Trail is closed while the MT 64 TIGER Grant project team evaluates needed repairs. A survey of the area has occurred, and project team members are working closely with the Big Sky Community Organization to create a repair plan. The project team anticipates repairs will be completed as early as material availability and weather allows next spring. The trail will remain closed until repairs are completed.

MDT, Gallatin County, and project contractors are grateful for the community's patience and support during this project.

Weekly updates will continue to be provided throughout construction.

Traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day from the project's main page.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

September 25-29, 2023

The Montana Department of Transportation (MDT) and Riverside Contracting Inc. are continuing work on the MT 64 TIGER Grant project. Here’s what you can expect for the week of September 25.

Paving operations are complete on Huntley Drive, Little Coyote Road, Big Sky Resort Road, Big Pine Drive, and Andesite Road, and the shared-use path between Big Pine Drive and Andesite Road. Paving through the pedestrian tunnel will occur in 2024.

Sign installation will occur this week in multiple project areas, and temporary striping activities will be completed on Tuesday, September 26, and Wednesday, September 27, weather permitting. While striping occurs, minimal traffic impacts can be expected. Crews will return next spring to complete the seal and cover (chip seal) and permanent striping in all project areas.

Final construction activities are taking place on the traffic signal at Little Coyote Road, which is anticipated to be activated on October 10.

The shared-use path between Big Pine Drive and Andesite Road is now open. A date for handrail installation has not yet been determined.

Landscaping activities and guardrail installation will occur in October. Reduced speeds and traffic shifts may be necessary while these activities are completed. No lane closures are anticipated.

Improvements near the intersection of Montana Highway 64 (MT 64) and US Highway 191 (US 191) will be completed during the 2024 construction season.

Kircher Park Trail is closed while the MT 64 TIGER Grant project team evaluates needed repairs. A survey of the area has occurred, and project team members are working closely with the Big Sky Community Organization to create a repair plan. Creating a plan for sustainable solutions and procuring materials is a long process. The project team anticipates repairs will be completed as early as material availability and weather allows next spring. Until repairs are completed, the trail will remain closed.

While we know construction is inconvenient, the project will benefit the Big Sky traveling public. MDT, Gallatin County, and project contractors are grateful for community patience and support during this project.

Weekly updates will continue to be provided throughout construction.

Traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day from the project's main page.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

September 18-22, 2023

The Montana Department of Transportation (MDT) and Riverside Contracting Inc. are conducting the MT 64 TIGER Grant project. Here’s what you can expect for the week of September 18.

Paving operations will resume Wednesday, September 20, and continue through Saturday, September 23. Crews will be paving in multiple project areas including Little Coyote Road, Huntley Drive, between Big Pine Drive and Andesite Road, and the shared-use path. Periodic single-lane closures and flaggers may be necessary. Drivers are encouraged to plan for extended delays.

Temporary striping activities are anticipated for the week of September 25. Crews will return next spring to complete seal and cover (chip seal) and permanent striping in all project areas.

Shared-use path closures are necessary to complete construction activities, and barriers are in place as a safety measure. Please do not manipulate or remove construction barriers to access the shared-use path.

A 12-foot width restriction is in place throughout the project area. Additional traffic control may be necessary as construction equipment is moved.

Construction will occur between 6 a.m. and 7 p.m. Crews will be present on weekdays and as necessary, on weekends to complete construction.

Weekly updates will continue to be provided throughout construction.

Traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day from the project's main page.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

September 11-15, 2023

The Montana Department of Transportation (MDT) and Riverside Contracting Inc. are continuing work on the MT 64 TIGER Grant project. Here’s what you can expect for the week of September 11.

Periodic single-lane closures and flaggers between Huntley Drive and Andesite Road may be necessary. Drivers are encouraged to plan for extended delays.

Paving operations are completed in several areas. The remaining paving work is anticipated for the week of September 18, weather and other factors permitting.

Concrete operations near Little Coyote Road are anticipated for completion on Friday, September 8. Remaining concrete work will occur the week of September 11. Minor traffic impacts are expected while concrete is poured.

The pedestrian bridge near Big Sky Community Park has been placed. Work near the park remains paused until shared-use path construction begins.

Construction continues on the shared-use path between Big Pine Drive and Andesite Road. Drivers can expect minimal traffic impacts and occasional flaggers while equipment is unloaded. Shoulder closures with flaggers are possible.

Shared-use path closures are necessary to complete construction activities, and barriers are in place as a safety measure. Please do not manipulate or remove construction barriers to access the shared-use path.

A 12-foot width restriction is in place throughout the project area. Additional traffic control may be necessary as construction equipment is moved.

Construction will occur between 6 a.m. and 7 p.m. Crews will be present on weekdays and on weekends as necessary to complete construction.

Weekly updates will continue to be provided throughout construction.

Traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day from the project's main page.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

September 4-8, 2023

The Montana Department of Transportation (MDT) and Riverside Contracting Inc. are conducting the MT 64 TIGER Grant project. Here’s what you can expect for the week of September 4.

Construction will pause on Monday, September 4, in observance of Labor Day and resume on Tuesday, September 5.

Paving is anticipated for Wednesday, September 6, near Big Sky Resort Road. Depending on availability of materials and crews, paving may also occur between Little Coyote Road and Huntley Drive later in the week. Periodic single-lane closures and flaggers will be necessary during paving operations. Drivers are encouraged to plan for extended delays.

Concrete operations near Little Coyote Road are anticipated for Tuesday, September 5 and Thursday, September 7. Minor traffic impacts can be expected.

The pedestrian bridge near Big Sky Community Park has been placed. Work near the park will pause until shared-use path construction begins.

Construction continues on the shared-use path between Big Pine Drive and Andesite Road. Drivers can expect minimal traffic impacts and occasional flaggers while equipment is unloaded. Shoulder closures with flaggers are possible.

Shared-use path closures are necessary to complete construction activities, and barriers are in place as a safety measure. Please do not manipulate or remove construction barriers to access the shared-use path.

A 12-foot width restriction is in place throughout the project area. Additional traffic control may be necessary as construction equipment is moved.

Construction will occur between 6 a.m. and 7 p.m. Crews will be present on weekdays and, as necessary, on weekends to complete construction.

Weekly updates will continue to be provided throughout construction.

Traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day from the project's main page.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

August 28-September 1, 2023

The Montana Department of Transportation (MDT), in partnership with Gallatin County and Riverside Contracting Inc., is conducting the MT 64 TIGER Grant project. Here’s what you can expect for the week of August 28.

Roadway paving over the pedestrian tunnel has been completed. Concrete crews will be on-site this week for curb, gutter, and Americans with Disabilities Act (ADA) sidewalk upgrades near Little Coyote Road.

Construction is underway to widen Montana Highway 64 (MT 64) to include a turn lane at Huntley Drive. Periodic single-lane closures and flaggers between Little Coyote Road and Huntley Drive may be necessary. Drivers are encouraged to plan for delays.

The pedestrian bridge near Big Sky Community Park has been placed. Work near the park will pause until shared-use pathway construction begins.

Construction continues on the shared-use path between Big Pine Drive and Andesite Road. Drivers can expect minimal traffic impacts and occasional flaggers while equipment is unloaded. Shoulder closures with flaggers are possible.

Shared-use path closures are necessary to complete construction activities and barriers are in place as a safety measure. Please do not manipulate or remove construction barriers to access the shared-use path.

A 12-foot width restriction is in place through the project area. Additional traffic control may be necessary as construction equipment is moved.

Construction will occur between 6 a.m. and 7 p.m. Crews will be present on weekdays and as necessary on weekends to complete construction.

Weekly updates will continue to be provided throughout construction.

Traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day from the project's main page.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

August 21-25, 2023

The Montana Department of Transportation (MDT), in partnership with Gallatin County and Riverside Contracting Inc., is conducting the MT 64 TIGER Grant project. Here’s what you can expect for the week of August 21.

Traffic is moving over the pedestrian tunnel near Little Coyote Road. Drivers can expect to travel on gravel surfaces until paving is complete. Weather permitting, crews plan to pave this portion of the project today, Friday, August 18. Concrete crews will be on-site next week for curb, gutter, and Americans with Disabilities Act (ADA) sidewalk upgrades on Little Coyote Road.

Construction is underway to widen Montana Highway 64 (MT 64) to include a turn lane at Huntley Drive. Single-lane closures and flaggers between Little Coyote Road and Huntley Drive can be expected. This means vehicles will be stopped at times to allow opposing traffic through the work zone. Drivers are encouraged to plan for delays.

The pedestrian bridge near Big Sky Community Park has been placed. Work near the park will pause until shared-use pathway construction begins this week.

Construction continues on the shared-use path between Big Pine Drive and Andesite Road. Drivers can expect minimal traffic impacts and occasional flaggers while equipment is unloaded. Shoulder closures with flaggers are possible.

Shared-use path closures are necessary to complete construction activities and barriers are in place as a safety measure. Please do not manipulate or remove construction barriers to access the shared-use path.

A 12-foot width restriction is in place. Additional traffic control may be necessary as construction equipment is moved through the area.

Construction will occur between 6 a.m. and 7 p.m. Crews will be present on weekdays and as necessary on weekends to complete construction.

Weekly updates will continue to be provided throughout construction.

Traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day from the project's main page.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

August 14-18, 2023

The Montana Department of Transportation (MDT), in partnership with Gallatin County and Riverside Contracting Inc., has begun work on the MT 64 TIGER Grant project. Here’s what you can expect for the week of August 14.

Traffic is moving over the pedestrian tunnel near Little Coyote Road. Drivers can expect to travel on gravel surfaces until paving operations occur. Paving on this portion of the project is anticipated for Friday, August 18, weather permitting.

Construction is underway to widen Montana Highway 64 (MT 64) for the turn lane at Huntley Drive. Expect single-lane closures and flaggers between Little Coyote Road and Huntley Drive. Drivers are encouraged to plan for delays as vehicles will be stopped periodically to allow traffic in the opposite direction to travel through the work zone.

The pedestrian bridge near Big Sky Community Park has been placed. Work near the park will pause briefly before construction begins on the shared-use pathway.

Construction continues on the shared-use path between Big Pine Drive and Andesite Road. Drivers can expect minimal traffic impacts and occasional flaggers while equipment is unloaded. Shoulder closures are possible.

Shared-use path closures are necessary to complete construction activities and barriers are in place as a safety measure. Please do not manipulate or remove construction barriers to access the shared-use path.

A 12-foot width restriction is in place. Additional traffic control may be necessary as construction equipment is moved through the area.

Construction will occur between 6 a.m. and 7 p.m. Crews will be present on weekdays and weekends as necessary to complete construction.

Weekly updates will be provided throughout construction.

Traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day from the project's main page.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

August 7-11, 2023

The Montana Department of Transportation (MDT), in partnership with Gallatin County and Riverside Contracting Inc., has begun work on the MT 64 TIGER Grant project. Here’s what you can expect for the week of August 7.

The detour has been removed near Little Coyote Road and traffic is moving over the pedestrian tunnel. Drivers can expect gravel surfaces for the next several days until paving operations occur.

Construction is underway to widen Montana Highway 64 (MT 64) for the turn lane at Huntley Drive. While road widening operations are underway, single-lane traffic and flaggers between Little Coyote Road and Huntly Drive will be necessary. Drivers are encouraged to plan for delays.

Crews will begin placing underground electrical lines near Little Coyote Road. These electrical lines will serve the pedestrian tunnel lighting and the traffic signal at the Little Coyote Road/MT 64 intersection. Installation of the traffic signal is anticipated for September.

The pedestrian bridge near Big Sky Community Park has been placed. Work near the park will pause briefly before shared-use pathway construction begins.

Construction has begun to improve the shared-use path between Big Pine Drive and Andesite Road. Drivers can expect minimal traffic impacts and occasional flaggers while equipment is unloaded. Shoulder closures with flaggers are possible.

A 12-foot width restriction is in place. Additional traffic control may be necessary as construction equipment is moved through the area.

Construction will occur between 6 a.m. and 7 p.m., Monday through Friday, weather and other factors permitting.

Weekly updates will be provided throughout construction.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

July 31-August 4, 2023

The Montana Department of Transportation (MDT), in partnership with Gallatin County and Riverside Contracting Inc., has begun work on the MT 64 TIGER Grant project. Here’s what you can expect for the week of July 31.

Crews are hard at work on pedestrian tunnel construction near Little Coyote Road. Traffic on Montana Highway 64 (MT 64) is being rerouted to a gravel detour. One travel lane remains open in each direction. Drivers are encouraged to maintain 25 mph speeds through the work zone to keep traffic moving. Workers will be present Saturday, July 29, and Sunday, July 30, to complete backfill operations.

Construction near Huntley Drive will begin mid-week. While road widening operations are underway, single-lane traffic and flaggers will be necessary between Little Coyote Road and Huntly Drive. Drivers are encouraged to plan for delays.

A 12-foot width restriction is in place. Additional traffic control may be necessary as construction equipment is moved through the area.

This week, the pedestrian bridge near Big Sky Community Park will be installed. The Little Coyote Road bridge will be closed on August 2 while the pedestrian bridge is delivered and placed.

Construction has begun to improve the shared-use path between Big Pine Drive and Andesite Road. Drivers can expect minimal traffic impacts and occasional flaggers while equipment is unloaded. Shoulder closures with flaggers will begin later this week to accommodate concrete trucks.

Construction will occur between 6 a.m. and 7 p.m., Monday through Friday, weather and other factors permitting.

Weekly updates will be provided throughout construction.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

July 24-28, 2023

The Montana Department of Transportation (MDT), in partnership with Gallatin County and Riverside Contracting Inc., has begun work on the MT 64 TIGER Grant project. Here’s what you can expect for the week of July 24.

Construction preparation for the pedestrian tunnel is underway. Traffic on Montana Highway 64 (MT 64) is being rerouted to a gravel detour west of Little Coyote Road. The detour is anticipated to move to the east side at the end of this week or early next week. One travel lane is open in each direction. Drivers are encouraged to maintain 25 mph speeds through the work zone to keep traffic moving.

A 12-foot width restriction is in place. Additional traffic control may be necessary as construction equipment is moved through the area.

Crews are preparing to install the pedestrian bridge near Big Sky Community Park. I Little Coyote Road bridge will be closed on August 2 while the pedestrian bridge is delivered and placed.

Construction activities are underway to improve the shared-use path between Big Pine Drive and Andesite Road. Drivers can expect minimal traffic impacts and occasional flaggers while equipment is unloaded. Shoulder closures with flaggers will begin later this week to accommodate concrete trucks.

Construction activities will occur between 6 a.m. and 7 p.m., Monday through Friday, weather and other factors permitting.

Weekly updates will be provided throughout construction.

Traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day from the project's main page.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

July 17-21, 2023

The Montana Department of Transportation (MDT), in partnership with Gallatin County and Riverside Contracting Inc., has begun work on the MT 64 TIGER Grant project. Here’s what you can expect for the week of July 17.

Construction preparation for the pedestrian tunnel is underway. Traffic on Montana Highway 64 (MT 64) is being rerouted to a gravel detour west of Little Coyote Road. One travel lane is open in each direction. Drivers are encouraged to maintain 25 mph speeds through the work zone to keep traffic moving.

A 12-foot width restriction is in place. Additional traffic control may be necessary as construction equipment is moved through the area.

Crews are preparing to install the pedestrian bridge near Big Sky Community Park. Access across the Little Coyote Road bridge will be closed on August 2 while the pedestrian bridge is delivered and placed.

Construction activities are underway to improve the shared-use path between Big Pine Drive and Andesite Road. Periodic single-lane closures are possible on MT 64 to accommodate construction vehicles and equipment moving through the work zone.

Drivers can expect construction activities to occur between 6 a.m. and 7 p.m., Monday through Friday, weather permitting.

Weekly updates will be provided throughout construction.

Traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day from the project's main page.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

July 10-14, 2023

The Montana Department of Transportation (MDT) in partnership with Gallatin County and Riverside Contracting Inc. has begun work on the MT 64 TIGER Grant project. Here’s what you can expect for the week of July 10.

Construction preparation for the pedestrian tunnel is underway. Traffic on Montana Highway 64 (MT 64) is being rerouted to a gravel detour west of Little Coyote Road. A 12-foot width restriction is in place. Additional traffic control may be necessary as construction equipment is moved through the area.

Work on the pedestrian bridge near Big Sky Community Park is ongoing. Crew have begun work on the bridge foundations, called footings. Expect periodic single-lane closures and flaggers on Little Coyote Road.

Construction activities are in progress to improve the shared-use path between Big Pine Drive and Andesite Road. Periodic single-lane closures are possible on MT 64 to accommodate construction vehicles and equipment moving through the work zone.

Drivers can expect construction activities to occur between 6 a.m. and 7 p.m., Monday through Friday, weather permitting.

Weekly updates will be provided throughout construction.

Traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day from the project's main page.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

July 3-7, 2023

The Montana Department of Transportation (MDT) in partnership with Riverside Contracting Inc. has begun work on the MT 64 TIGER Grant project. Here’s what you can expect for the week of July 3.

Work will pause Monday, July 3 and Tuesday, July 4 for Independence Day.

Construction preparation for the pedestrian tunnel has begun. Traffic on Montana Highway 64 (MT 64) will be rerouted to a gravel detour west of Little Coyote Road beginning July 5. A 12-foot width restriction is in place. Additional traffic control may be necessary as construction equipment is moved through the area. Please be mindful of crews working and reduced speeds.

Work on the pedestrian bridge near Big Sky Community Park is ongoing. Expect periodic single-lane closures and flaggers on Little Coyote Road.

Additional construction activities will begin on the shared-use path between Big Pine Drive and Andesite Road. Minor traffic impacts can be expected, and construction vehicles and equipment are moved through the work zone.

Drivers can expect construction activities to occur between 6 a.m. and 7 p.m., Monday through Friday, weather permitting.

Weekly updates will be provided throughout construction.

Two traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

June 26-30, 2023

Riverside Contracting crews have begun construction on the MT 64 TIGER Grant project. Here’s what you can expect the week of June 26.

Work on the pedestrian bridge near Big Sky Community Park is ongoing. Expect periodic single-lane closures and flaggers on Little Coyote Road.

Construction preparation for the pedestrian tunnel has begun. Traffic on Montana Highway 64 (MT 64) will be rerouted to a gravel detour west of Little Coyote Road. A 12-foot width restriction is in place. Additional traffic control may be necessary as construction equipment is moved through the area. Please be mindful of crews working and reduced speeds.

Drivers can expect construction activities to occur between 6 a.m. and 7 p.m., Monday through Friday, weather permitting.

Weekly updates will be provided throughout construction.

Two traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

June 19-23, 2023

Riverside Contracting crews have begun construction on the MT 64 TIGER Grant project.

Work continues on the pedestrian bridge near Big Sky Community Park. Expect periodic single-lane closures and flaggers on Little Coyote Road.

Construction on the pedestrian tunnel will begin this week. By the end of the week, traffic on Montana Highway 64 (MT 64) will be rerouted to a gravel detour west of Little Coyote Road. A 12-foot width restriction is in place. Additional traffic control may be periodically necessary as construction equipment is moved through the area.

Drivers can expect construction activities to occur between 6 a.m. and 7 p.m., Monday through Friday, weather permitting.

Weekly updates will be provided throughout construction.

Two traffic cameras have been provided by Big Sky Resort Tax Area. These cameras can be accessed 24 hours a day.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

June 12-16, 2023

Work continues on the pedestrian bridge near Big Sky Community Park, Single-lane closures and flaggers are in place on Little Coyote Road.

Crews will strip topsoil near the shared-use path between Big Pine Drive and Andesite Road. A 12-foot width restriction will begin this week on Montana Highway 64 (MT 64). Additional traffic control may be periodically necessary as construction equipment is moved through the area.

Drivers can expect construction activities to occur between 6 a.m. and 7 p.m., Monday through Friday. All work is weather dependent.

Construction on the pedestrian tunnel is anticipated to begin the week of June 19, although some operations may begin as early as the end of next week.

Weekly updates will be provided throughout construction.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

June 5-9, 2023

Riverside Contracting will begin construction on the MT 64 TIGER Grant the week of June 5. Work will begin near Little Coyote Road and the Big Sky Community Park.

Drivers can expect to see crews completing initial surveying, stripping topsoil, and driving piles of material to the project area this week. Traffic control will include a single lane closure for a short stretch of Little Coyote Road near the Big Sky Community Park. Drivers will be directed by flaggers through the work zone. Please anticipate a few minutes of delay.

Weekly updates will be provided throughout construction.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

May 29 - June 2, 2023

Riverside Contracting crews are preparing for the start of MT 64 TIGER Grant construction. Work will begin near Little Coyote Road the week of June 5. Drivers can expect single-lane closures while construction is underway. Weekly updates will be provided throughout construction.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.

May 22-26, 2023

Riverside Contracting crews are preparing for the MT 64 TIGER Grant project construction. The slow arrival of spring has delayed the project start date. Construction is now anticipated to begin in early June. In the coming weeks, crews will begin to mobilize equipment as access to staging areas becomes available.

Weekly updates will be provided throughout construction.

If you have questions, please email Kristine at KristineXYZbigskypublicrelationsABCcom. Our project hotline is also open Monday through Friday from 9 a.m. to 5 p.m. at 406-207-4484.

Text updates are available. To sign up, text MT64PROJECT to 41411.