November 20-22, 2023

Activities:

  • The Montana Department of Transportation (MDT) and Sletten Construction crews are working Monday, November 20, through Wednesday, November 22, from 7 a.m. to 5 p.m., weather and other factors permitting.
  • Before Thanksgiving, traffic control on Interstate 90 (I 90) at the Yellowstone River will be removed and three travel lanes will be open in each direction. Watch for changing traffic patterns when traveling through the project area.
  • Ongoing work includes signage installation, work bridge removal, and miscellaneous cleanup activities.
  • Help keep construction workers and other drivers safe by following all posted signage.

Width Restrictions:

  • No width restrictions are in place.

Work Zone Cameras and 511:

Work bridge removal

Work bridge removal

November 14, 2023

Activities:

  • The Montana Department of Transportation (MDT) and Sletten Construction crews are working Monday, November 13, through Friday, November 17, from 7 a.m. to 5 p.m., weather and other factors permitting.
  • Single-lane closures are in place on east and westbound Interstate 90 (I 90). Watch for changing traffic patterns and width restrictions.
    • Three lane traffic in each direction is scheduled to open the week of Thanksgiving.
  • Crews are continuing to pave the roadway, complete barrier construction and roadway striping activities, install signage, and removing the work bridge.
  • There is extensive hauling and truck traffic throughout the project area. Please pay attention.

Current I 90 Closures:

  • Ramp closure – The Lockwood Interchange westbound on-ramp is anticipated to open this week.

Width Restrictions:

  • NOTE: I 90 width restrictions are in place for loads 16 feet and over. No accommodations can be made due to the construction location. Traffic exceeding 16 feet should find an alternate route.

Work Zone Cameras and 511:

Roadway construction continues.

Roadway construction continues.

November 6-12, 2023

Activities:

  • The Montana Department of Transportation (MDT) and Sletten Construction crews are working Monday, November 6, through Sunday, November 12, from 6 a.m. to 5:30 p.m., weather and other factors permitting.
  • Single-lane closures are in place on east and westbound Interstate 90 (I 90). Watch for changing traffic patterns and width restrictions.
    • Two lane traffic in each direction is scheduled to open during the week of November 13. Some construction will continue throughout the winter.
  • Roadway paving and traffic barrier construction continues. The work bridge will be removed this week.
  • There is extensive hauling and truck traffic throughout the project area. Please pay attention.

Current I 90 Closures:

  • Ramp closure – MDT and Sletten anticipate opening the Lockwood Interchange westbound on-ramp during the week of November 13. Schedule updates will be provided as progress is made.

Upcoming I 90 Closures:

  • I 90 closure – NOTE DATE CHANGE: Monday, November 6, 9 p.m., all I 90 eastbound lanes between the 27th Street and Lockwood interchanges will be closed for about four hours. An overhead sign support structure will be installed and use of a crane in the roadway is required. A detour route will be provided.

Width Restrictions:

  • NOTE: I 90 width restrictions are in place for loads 16 feet and over. No accommodations can be made due to the construction location. Traffic exceeding 16 feet should find an alternate route.

Work Zone Cameras and 511:

Installation of the 54” concrete barrier wall.

Installation of the 54” concrete barrier wall.

October 30, 2023

Activities:

  • Sletten Construction crews are working Monday, October 30, through Sunday, November 5, from 6 a.m. to 5:30 p.m., weather and other factors permitting.
  • Single-lane traffic remains on east and westbound Interstate 90 (I 90). Watch for changing traffic patterns and width restrictions.
  • Roadway and bridge work includes ongoing traffic barrier construction.
  • There is extensive hauling and truck traffic throughout the project area. Please pay attention.

Current I 90 Closures:

  • Ramp closure – Work began Monday, October 23, the Lockwood Interchange westbound on-ramp is closed. The closure is anticipated to last three weeks, weather and other factors permitting. Schedule updates will be provided as progress is made.

Upcoming I 90 Closures:

  • I 90 closure – Tuesday, November 7, 9 p.m., all I 90 eastbound lanes between the 27th Street and Lockwood interchanges will be closed for about four hours, weather and other factors permitting. An overhead sign support structure will be installed and use of a crane in the roadway is required. Updates will be provided as the date gets closer.

Width Restrictions:

  • NOTE: I 90 width restrictions are in place for loads 16 feet and over. No accommodations can be made due to the construction location. Traffic exceeding 16 feet should find an alternate route.

Work Zone Cameras and 511:

Paving eastbound I 90.

Paving eastbound I 90.

October 23, 2023

Activities:

  • Sletten Construction crews are working Monday, October 23, through Sunday, October 29, from 6 a.m. to 5:30 p.m.
  • Single-lane traffic remains on east and westbound Interstate 90 (I 90) but watch for changing traffic patterns and width restrictions.
  • Roadway and bridge work includes ongoing traffic barrier construction.
  • Extensive hauling and truck traffic on the project. Please pay attention.

I 90 Closures:

  • I 90 closure – Monday night, October 23, all I 90 westbound lanes between the Lockwood and 27th Street interchanges will be closed for about four hours starting at 9 p.m., weather and other factors permitting. An overhead sign support structure will be installed and use of a crane in the roadway is required.
  • Ramp closure – Starting Monday, October 23, the Lockwood Interchange westbound on-ramp will be closed. The closure is anticipated to last three weeks, weather and other factors permitting. Schedule updates will be provided as progress is made.

Upcoming Activities:

  • I 90 closure – Starting the second week of November, all I 90 eastbound lanes between the 27th Street and Lockwood interchanges will be closed for about four hours, weather and other factors permitting. An overhead sign support structure will be installed and use of a crane in the roadway is required. Updates will be provided as the date draws near.

Width Restrictions:

  • NOTE:I 90 width restrictions are in place for loads 16 feet and over. No accommodations can be made due to the construction location. Traffic exceeding 16 feet should find an alternate route.

Work Zone Cameras and 511:

Installation of the 54” barrier wall.

Installation of the 54” barrier wall.

October 16, 2023

Activities:

  • Sletten Construction crews are working Monday, October 16, through Sunday, October 22, from 6 a.m. to 5:30 p.m.
  • Single-lane traffic remains on east and westbound Interstate 90 (I 90). Watch for changing traffic patterns and width restrictions.
  • Eastbound bridge work includes ongoing traffic barrier construction.
  • Extensive hauling and truck traffic on the project. Please pay attention.

Upcoming Activities:

  • Ramp closure – Construction and paving of the westbound on-ramp will occur at the Lockwood Interchange beginning Monday, October 23. The closure likely will last two weeks, weather and other factors permitting. Updates will be provided as the date draws near.
  • I 90 closure – I 90 will be closed for two hours Tuesday night, October 24, weather and other factors permitting. An overhead sign support structure will be installed and use of a crane in the roadway is required. Updates will be provided as the date draws near.

Width Restrictions:

  • NOTE: I 90 width restrictions are in place for loads 16 feet and over. No accommodations can be made due to the construction location. Traffic exceeding 16 feet should find an alternate route.

Work Zone Cameras and 511:

Median curb work at the Lockwood exit

Median curb work at the Lockwood exit.

October 7, 2023

Activities:

  • Sletten Construction crews are working Saturday, October 7, through Sunday, October 15, from 6 a.m. to 5:30 p.m.
  • Beginning Saturday, October 7, through Monday, October 9, traffic will be moved to westbound passing lanes on the Yellowstone River Bridge, weather and other factors permitting. Otherwise, single-lane traffic will remain on east and westbound roadways with width restrictions in place. Watch for changing traffic patterns.
  • Eastbound Interstate 90 (I 90) roadway and shoulder paving, guardrail, and lighting installations are ongoing. Eastbound bridge work includes traffic barrier construction.
  • Extensive hauling and truck traffic on the project. Please pay attention and follow traffic control.

Width Restrictions:

  • NOTE: I 90 width restrictions are in place for loads 16 feet and over. No accommodations can be made due to the construction location. Traffic exceeding 16 feet should find an alternate route.

Work Zone Cameras and 511:

Crews building concrete road barriers.

Crews building concrete road barriers.

October 2, 2023

Activities:

  • Sletten Construction crews are working Monday, October 2, through Saturday, October 7, from 6 a.m. to 5:30 p.m.
  • Eastbound Interstate 90 (I 90) roadway and shoulder paving, guardrail, and lighting installations are ongoing. Eastbound bridge work includes traffic barrier construction.
  • Beginning Wednesday, October 4, weather and other factors permitting, watch for changing traffic patterns including:
    • Traffic will no longer travel on the same side of I 90, and use of crossovers will end. Single-lane traffic will remain on east and westbound roadways with width restrictions in place.
    • Lockwood eastbound off-ramp will be opened.
  • Please drive carefully and observe all posted speed limits.

Width Restrictions:

  • NOTE: Beginning Wednesday, October 4, I 90 width restrictions are in place for loads 16 feet and over. No accommodations can be made due to the construction location. Traffic exceeding 16 feet should find an alternate route.

Work Zone Cameras and 511:

Crews installing highway direction signs

Crews installing highway direction signs

September 24, 2023

Activities:

  • Sletten Construction crews are working Sunday, September 24, through Saturday, September 30, 6 a.m. to 5:30 p.m.
  • Ramp closures and anticipated openings:
    • The 27th Street eastbound on-ramp is open!
    • The Lockwood eastbound off-ramp is closed. Crews expect to open the ramp October 4, weather and other factors permitting.
  • Eastbound Interstate 90 (I 90) paving and bridge construction is ongoing.
  • The eastbound far right lane is dedicated to construction trucks and equipment. Please pay attention and follow traffic control.

Width Restrictions:

  • NOTE: Eastbound I 90 width restrictions are in place for loads 16 feet and over. No accommodations can be made due to the construction location. Eastbound traffic exceeding 16 feet should find an alternate route.
  • Westbound I 90 width restrictions are in place for loads 22 feet and over.
  • Wide load accommodations for westbound traffic including a staging area have been provided. Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Workers place the concrete barrier rail on the eastbound bridge

Workers place the concrete barrier rail on the eastbound bridge

September 18, 2023

Activities:

  • Sletten Construction crews are working Monday through Saturday, 6 a.m. to 5:30 p.m.
  • Good news! Eastbound roadway paving is underway.
  • Ramp closures and anticipated openings:
    • The 27th Street eastbound on-ramp is closed. Crews expect to open the ramp mid-week, weather and other factors permitting.
    • The Lockwood eastbound off-ramp was closed Tuesday, September 5. The closure is anticipated to last four weeks, weather and other factors permitting.
  • East and westbound traffic remain one lane in each direction. No driving or parking is permitted on the roadway shoulders.

Width Restrictions:

  • NOTE: Eastbound Interstate 90 (I 90) width restrictions are in place for loads 16 feet and over. No accommodations can be made due to the construction location. Eastbound traffic exceeding 16 feet should find an alternate route.
  • Westbound I 90 width restrictions are in place for loads 22 feet and over.
  • Wide load accommodations for westbound traffic including a staging area have been provided. Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Installing eastbound roadway pavement

Installing eastbound roadway pavement!

September 11, 2023

Activities:

  • Sletten Construction crews are working Monday through Saturday, 6 a.m. to 5:30 p.m.
  • Ramp closures – Please note the following ramp closures:
    • The 27th Street eastbound on-ramp is closed. The closure is anticipated to last one more week, weather and other factors permitting.
    • The Lockwood eastbound off-ramp was closed Tuesday, September 5. The closure is anticipated to last four weeks, weather and other factors permitting.
  • East and westbound traffic remain one lane in each direction. No driving or parking is permitted on the roadway shoulders.

Width Restrictions:

  • NOTE: Eastbound Interstate 90 (I 90) width restrictions are in place for loads 16 feet and over. No accommodations can be made due to the construction location. Eastbound traffic exceeding 16 feet should find an alternate route.
  • Westbound I 90 width restrictions are in place for loads 22 feet and over.
  • Wide load accommodations for westbound traffic including a staging area have been provided. Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Installing a reinforced concrete storm drainpipe

Installing a reinforced concrete storm drainpipe.

September 4, 2023

Activities:

  • Sletten Construction crews are working Tuesday through Friday, 6 a.m. to 5:30 p.m. Construction will be paused Monday, September 4, for Labor Day.
  • Ramp closures – Commuters, please note the following upcoming ramp closures.
    • The 27th Street Interchange eastbound on-ramp was closed Monday, August 28, and closure is anticipated to last three weeks, weather and other factors permitting.
    • The Lockwood Interchange eastbound off-ramp will be closed starting Tuesday, September 5. This closure is anticipated to last four weeks, weather and other factors permitting.
  • Good news! The eastbound bridge deck concrete pour is complete.
  • East and westbound traffic remain one lane in each direction. No driving or parking is permitted on the roadway or bridge shoulders.

Width Restrictions:

  • NOTE: Eastbound I 90 width restrictions will be in place for loads 13 feet and over starting Monday, August 28. No accommodations can be made due to construction location. Eastbound traffic exceeding 13 feet should find an alternate route.
  • Westbound I 90 width restrictions are in place for loads 22 feet and over.
  • Wide load accommodations for westbound traffic including a staging area have been provided. Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Final bridge deck concrete pour

Final bridge deck concrete pour!

August 28, 2023

Activities:

  • Sletten Construction crews are working Monday through Friday, 6 a.m. to 5:30 p.m.
  • Bridge work – Pouring concrete for the eastbound bridge deck continues this week.
    • Night work is scheduled for Tuesday, August 29 through Wednesday, August 30.
    • Use of no-glare construction lights will be used.
    • Expect an increase in concrete truck traffic during bridge deck pours. Please drive cautiously.
  • Ramp closures – Commuters, please note the following upcoming ramp closures.
    • The 27th Street eastbound on-ramp will be closed starting Monday, August 28. This closure is anticipated to last three weeks, weather and other factors permitting.
    • The Lockwood eastbound off-ramp will be closed starting Tuesday, September 5. This closure is anticipated to last four weeks, weather and other factors permitting.
  • Please be aware of crews and heavy equipment when traveling through the project area.

Width Restrictions:

  • NOTE: Eastbound I 90 width restrictions will be in place for loads 13 feet and over starting Monday, August 28. No accommodations can be made due to construction location. Eastbound traffic exceeding 13 feet should find an alternate route.
  • Westbound I 90 width restrictions are in place for loads 22 feet and over.
  • Wide load accommodations for westbound traffic including a staging area have been provided. Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Upcoming ramp closures.

Upcoming ramp closures.

August 21, 2023

Activities:

  • Sletten Construction crews are working Monday through Friday, 6 a.m. to 5:30 p.m.
  • Bridge work – Pouring concrete for the eastbound bridge deck begins this week.
    • Night work is scheduled for Tuesday, August 22, Thursday, August 24, and Tuesday through Wednesday, August 29 to 30.
    • Use of no-glare construction lights will be used.
    • Expect an increase in concrete truck traffic during bridge deck pours. Please drive cautiously.
  • Ramp work – Commuters, please note the following upcoming ramp closures.
    • The 27th Street eastbound on-ramp will be closed starting Monday, August 28. This closure is anticipated to last three weeks, weather and other factors permitting.
    • The Lockwood eastbound off-ramp will be closed starting Tuesday, September 5. This closure is anticipated to last four weeks, weather and other factors permitting.
  • Please be aware of crews and heavy equipment when traveling through the project area.

Width Restrictions:

  • Width restrictions are in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Installation of the bridge deck forming system continues in preparation for pouring concrete.

Installation of the bridge deck forming system continues in preparation for pouring concrete.

August 14, 2023

Activities:

  • Sletten Construction crews are working Monday through Friday, 6 a.m. to 5:30 p.m., with night work starting Tuesday, August 22.
  • In preparation for pouring concrete later this month, construction of the eastbound bridge superstructure continues with installation of the deck forming system.
  • East and westbound traffic remain one lane in each direction. Please be aware of crews and gravel hauling trucks when traveling through the project area. No driving or parking is permitted on the roadway shoulders.

Width Restrictions:

  • Width restrictions are in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Installation of the eastbound bridge superstructure

Installation of the eastbound bridge superstructure.

August 7, 2023

Activities:

  • Sletten Construction crews are working Monday through Friday, 6 a.m. to 5:30 p.m. Night work will begin on Tuesday, August 22.
  • Construction of the eastbound bridge superstructure continues with pouring the concrete approaches. Pouring the concrete deck will begin later this month.
  • East and westbound traffic remain one lane in each direction. No driving or parking on the roadway shoulders through the construction zone.

Width Restrictions:

  • Width restrictions are in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Installation of the eastbound bridge superstructure deck forming system.

Installation of the eastbound bridge superstructure deck forming system.

July 31, 2023

Activities:

  • Sletten construction crews working Monday through Sunday, 6 a.m. to 5:30 p.m.
  • Construction of the eastbound bridge superstructure continues with pouring the concrete approaches.
  • East and westbound traffic remain one lane in each direction. No driving or parking on the shoulders.

Width Restrictions:

  • Width restrictions are in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Pouring the concrete approach for the eastbound bridge superstructure deck.

Pouring the concrete approach for the eastbound bridge superstructure deck.

July 24, 2023

Activities:

  • Sletten construction crews working Monday through Sunday, 6 a.m. to 7:30 p.m.
  • East and westbound traffic remain one lane in each direction. No driving or parking on the shoulders.
  • Construction of the eastbound bridge superstructure continues with installation of the deck forming system.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Installation of the eastbound bridge superstructure deck forming system.

Installation of the eastbound bridge superstructure deck forming system.

July 17, 2023

Activities:

  • Sletten Construction crews are working Monday through Sunday, 6 a.m. to 7:30 p.m.
  • Please be aware of construction workers in the project area and drive safely.
  • Construction of the eastbound bridge superstructure continues with installation of the deck forming system.
  • Roadway grading work is upcoming but will not impact traffic.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Workers torquing the bridge beam bolts

Workers torquing the bridge beam bolts.

July 7, 2023

Activities:

  • Sletten construction crews working Monday through Sunday, 6 a.m. to 7:30 p.m., but no work 7/9.
  • Please be aware of crews and heavy equipment when traveling through the project area.
  • Construction of the eastbound bridge superstructure continues. There is one steel bridge beam left to place before crews will begin installing the deck forming system.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Crews placing the final steel bridge beams

Crews placing the final steel bridge beams. Great work team!

July 3, 2023

Activities:

  • Sletten crews will be working Monday through Sunday, 7 a.m. to 7:30 p.m. Work will be paused July 1 through July 4 for holiday break.
  • Only one travel lane in each direction for east and westbound traffic.
  • Construction of the eastbound bridge superstructure continues. The crews are almost finished placing the steel bridge beams.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

4th of July fireworks

Happy 4th of July!

June 26, 2023

Activities:

  • Sletten crews will be working Monday through Sunday, 7 a.m. to 7:30 p.m. Work will be paused July 1 through July 4 for holiday break.
  • East and westbound traffic remain one lane in each direction. Please be aware of crews and heavy equipment when traveling through the project area. No driving or parking on the shoulders.
  • Construction of the eastbound bridge superstructure continues. Six to eight bridge beams, called girders, are being delivered to the project site each day.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Placement of the girders on the eastside Yellowstone River bridge.

Placement of the girders on the eastside Yellowstone River bridge.

June 19, 2023

Activities:

  • Crews will be working Monday through Sunday, 7 a.m. to 7:30 p.m. Work will be paused July 1 through July 4.
  • Eastbound far right lane for construction trucks and equipment. Please pay attention.
  • Construction of the eastbound bridge superstructure continues. Received first bridge beam from TrueNorth Steel.
  • The Talen Energy RR structure is nearly complete.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Delivery of first bridge beam from TrueNorth Steel.

Delivery of first bridge beam from TrueNorth Steel.

June 12, 2023

Activities:

  • The eastbound far right lane is dedicated to construction trucks and equipment, and will be used to move the large bridge beams. Please pay attention.
  • Construction of the eastbound bridge spans begin, which is part of the superstructure. The superstructure is what supports the roadway we drive on.
  • The final precast panel arches have been installed on the Talen Energy RR structure.
  • Crews will be working Monday through Sunday, 7 a.m. to 7:30 p.m.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

The final precast panel arches have been installed on the Talen Energy RR structure.

The final precast panel arches have been installed on the Talen Energy RR structure.

June 5, 2023

Activities:

  • Expect single lane traffic, minor delays. Please be aware of crews and heavy equipment when traveling through the project area.
  • Construction of the eastbound bridge supports and Talen Energy RR arches is nearly complete.
  • Crews will be working Monday through Sunday, 7 a.m. to 7:30 p.m.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday through Friday, 3:30 to 5:30 a.m.

Work Zone Cameras and 511:

Riverside Construction is backfilling and compacting the soil behind the bridge’s concrete backwall to provide additional stabilization.

Riverside Construction is backfilling and compacting the soil behind the bridge’s concrete backwall to provide additional stabilization.

May 29, 2023

Activities:

  • Crews will be working Monday through Sunday, 7 a.m. to 7:30 p.m. No construction work from noon May 26 through May 29. Happy Memorial Day!
  • Workers continue building bridge supports, installing riprap on the shoreline around the west side of the bridge, and setting arches for the Talen Energy RR structure.
  • East and westbound traffic remain one lane in each direction. Please be aware of crews and heavy equipment when traveling through the project area.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday-Friday, 3:30-5:30 a.m.

Work Zone Cameras and 511:

Work continues on the new eastbound Yellowstone River bridge.

Work continues on the new eastbound Yellowstone River bridge.

May 22, 2023

Activities:

  • Crews will be working Monday through Sunday, 7 a.m. to 7:30 p.m. No construction work starting noon May 26 through May 29. Happy Memorial Day!
  • Workers continue pouring concrete for the eastbound bridge supports and building supporting arches for the Talen Energy RR structure.
  • Only one travel lane in each direction for east and westbound traffic. Please be aware of crews and heavy equipment.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday-Friday, 3:30-5:30 a.m.

Work Zone Cameras and 511:

To help protect the riverbank, Riverside Contracting is installing riprap, or large rock, around the west side of the Yellowstone River Bridge. The fabric placed under the riprap helps to stabilize the rock.

To help protect the riverbank, Riverside Contracting is installing riprap, or large rock, around the west side of the Yellowstone River Bridge. The fabric placed under the riprap helps to stabilize the rock.

May 15, 2023

Activities:

  • Crews will be working Monday-Sunday, 7 a.m.-7:30 p.m. No work over Memorial Day weekend.
  • Construction continues on the eastbound bridge and Talen Energy RR structure.
  • Only one travel lane in each direction for east and westbound traffic. Be aware of truck traffic and heavy equipment.

Happy Mother's Day!

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday-Friday, 3:30-5:30 a.m.

Work Zone Cameras and 511:

Placing concrete for the new Talen Rail Spur structure foundations, which will support the eastbound I 90 lanes.

Placing concrete for the new Talen Rail Spur structure foundations, which will support the eastbound I 90 lanes.

May 8, 2023

Activities:

  • Lanes are being restriped; traffic will be slowed temporarily.
  • Crews will be working 7 a.m.-7:30 p.m., Monday-Saturday. No work over Memorial Day weekend.
  • Construction on the eastbound bridge support piers continues.
  • Workers are driving the foundation-supporting piles at the Talen Energy RR structure.
  • Only one travel lane in each direction for east and westbound traffic. Be aware of truck traffic.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday-Friday, 3:30-5:30 a.m.

Work Zone Cameras and 511:

Contractor is setting preassembled concrete formwork for the upper portion of the concrete piers.

Contractor is setting preassembled concrete formwork for the upper portion of the concrete piers.

May 1, 2023

Activities:

  • Drill shafts are being built as part of the eastbound bridge support. Drill shafts are deep foundations constructed by drilling deep holes and filling them with reinforcing steel and concrete.
  • Crews will be working 7 a.m.-7:30 p.m., Monday-Saturday, with occasional Sunday work.
  • Only one travel lane in each direction for east and westbound traffic. No passing.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday-Friday, 3:30-5:30 a.m.

Work Zone Cameras and 511:

Crews and equipment drilling below the riverbed to build the new concrete foundations for the eastbound bridge.

Crews and equipment drilling below the riverbed to build the new concrete foundations for the eastbound bridge.

April 24, 2023

Activities:

  • Work hours: 7 a.m.-7:30 p.m., seven days a week.
  • There is only one lane in each direction for east and westbound traffic. No passing.
  • Construction on the eastbound bridge shafts, piers, and vertical abutments continue, all of which are part of the bridge superstructure and support the roadway.
  • Workers are driving the foundation-supporting piles at the Talen Energy RR structure.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday-Friday, 3:30-5:30 a.m.

Work Zone Cameras and 511:

Installing the drilled shafts for an eastbound bridge pier.

Installing the drilled shafts for an eastbound bridge pier.

April 17, 2023

Activities:

  • Work hours: 7 a.m.-7:30 p.m., seven days a week.
  • There is only one lane in each direction for east and westbound traffic. No passing.
  • Milling the eastbound I 90 roadway is complete. Milling is the process of removing a layer of asphalt from a paved surface.
  • Work continues on the eastbound bridge and Talen Energy RR structure

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday-Friday, 3:30-5:30 a.m.

Work Zone Cameras and 511:

Crews and equipment are utilizing the temporary work bridge to install foundations for the new eastbound bridge

Crews and equipment are utilizing the temporary work bridge to install foundations for the new eastbound bridge.

April 10, 2023

Activities:

  • Demolition of the old eastbound Yellowstone River bridge is now complete.
  • There is only one lane in each direction for east and westbound traffic. No passing.
  • Work hours: 7 a.m.-7:30 p.m. No Sunday construction work.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday-Friday, 3:30-5:30 a.m.

Work Zone Cameras and 511:

Removal of the old eastbound bridge is now complete. Work crews took advantage of low flows to remove the last pier.

Removal of the old eastbound bridge is now complete. Work crews took advantage of low flows to remove the last pier.

April 3, 2023

Activities:

  • There is only one lane each for east and westbound traffic. No passing. Pay attention to traffic control devices including orange candlesticks and barrels.
  • Demolition of the eastbound Yellowstone River bridge continues.
  • Work continues on the eastbound Talen Energy RR structure.
  • Work hours: 7 a.m.-7:30 p.m. No construction work April 9.

Width Restrictions:

  • Width restrictions in place for loads 22 feet and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area Monday-Friday, 3:30-5:30 a.m.

Work Zone Cameras and 511:

Eastbound bridge demolition continues. In this photo, crews are removing the existing steel girders.

Removal of the existing eastbound Talen Energy Rail Spur bridge is underway in preparation for extending the concrete arch structure shown to right.

March 27, 2023

Activities:

  • Slow down and be aware of construction workers and equipment.
  • The side of the road is for emergencies only, not for taking photos.
  • Demolition of the eastbound Yellowstone River bridge continues. The superstructure has been removed (that’s the part you drive on).
  • Work is beginning on the eastbound Talen Energy RR structure.
  • Work hours: 7 a.m.-7:30 p.m. including weekend work. Construction lights may be used.

Width Restrictions:

  • Width restrictions in place for loads 22 ft and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area M-F, 3:30-5:30 a.m.

Work Zone Cameras and 511:

Eastbound bridge demolition continues. In this photo, crews are removing the existing steel girders.

Eastbound bridge demolition continues. In this photo, crews are removing the existing steel girders.

March 20, 2023

Activities:

  • The eastbound off ramp to Lockwood now has a dedicated lane for construction trucks and equipment. Pay attention to new traffic controls.
  • Demolition to the eastbound Yellowstone River bridge continues. Use the side of the road for emergencies only.
  • Eastbound traffic has been detoured through crossovers to a two-way configuration in the westbound lanes.
  • Work hours: 7 a.m.-7 p.m., including weekend work. Construction lights will be used, as needed.

Width Restrictions:

  • Width restrictions in place for loads 22 ft and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area M-F, 3:30-5:30 a.m.

Work Zone Cameras and 511:

Removal of the existing eastbound bridge continues

Removal of the existing eastbound bridge continues!

March 13, 2023

Activities:

  • Starting this week, the eastbound off ramp to Lockwood will have a dedicated lane for construction trucks and equipment. Pay attention to new traffic controls.
  • Yellowstone River bridge demolition continues for 3 weeks. Stop on the side of the road for emergencies only.
  • Eastbound traffic has been detoured through crossovers to a two-way configuration in the westbound lanes.
  • Work hours: 7 a.m.-7 p.m., including weekend work. Construction lights will be used, as needed.

Width Restrictions:

  • Width restrictions in place for loads 22 ft and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area M-F, 3:30-5:30 a.m.

Work Zone Cameras and 511:

Demolition of the existing eastbound Yellowstone River bridge is underway starting at the east end

Demolition of the existing eastbound Yellowstone River bridge is underway starting at the east end.

March 4, 2023

Activities:

  • New traffic control begins Saturday morning, March 4, 2023
    • Eastbound traffic will be detoured through crossovers to a two-way configuration in the westbound lanes and will remain until November 2023.
    • Please drive carefully and observe all posted speed limits.
  • Work hours: 7 a.m.-7 p.m., including weekend work. Construction lights will be used, as needed.

Width Restrictions:

  • Width restrictions in place for loads 22 ft and over.
    • Wide load accommodations and a staging area have been provided.
    • Trucks are being guided through the area M-F, 3:30-5:30 a.m.

Work Zone Cameras and 511:

Temporary work bridge is complete, and crews are preparing to remove the existing eastbound bridge.

Temporary work bridge is complete, and crews are preparing to remove the existing eastbound bridge.

February 27, 2023

Activities:

  • New traffic control begins early to mid-March, weather dependent.
    • Eastbound traffic will be detoured through crossovers to a two-way configuration in the westbound lanes and will remain until November 2023.
    • Please drive carefully and observe all posted speed limits.
  • Work hours: 7 a.m.-7:30 p.m., including weekend work. Construction lights will be used, as needed.

Width Restrictions:

  • Width restrictions in place for loads 15’ and over.
    • Wide load accommodations and a staging area have been provided.
    • Trucks are being guided through the area M-F, 3:30-5:30 a.m.

Work Zone Cameras and 511:

The temporary work bridge is near completion and will be used to construct the new eastbound I 90 bridge.

The temporary work bridge is near completion and will be used to construct the new eastbound I 90 bridge.

February 20, 2023

Activities:

  • New traffic control begins February 27, 2023, weather dependent. Plan ahead.
  • Eastbound traffic will be detoured through crossovers to a two-way configuration in the westbound lanes.
    • Detour begins early March and will remain until November 2023.
    • Please drive carefully and observe all posted speed limits.
  • Work hours: 7 a.m.-7:30 p.m., including weekend work. Construction lights will be used, as needed.

Width Restrictions:

  • Width restrictions in place for loads 15’ and over.
    • Wide load accommodations and a staging area have been provided.
    • Trucks are being guided through the area M-F, 3:30-5:30 a.m.

Work Zone Cameras and 511:

The temporary work bridge is near completion and will be used to construct the new eastbound I 90 bridge.

The temporary work bridge is near completion and will be used to construct the new eastbound I 90 bridge.

February 13, 2023

Activities:

  • It’s nearly time for bridge and roadway construction!
  • New traffic control begins February 27, 2023, weather dependent.
  • The eastbound work bridge will be finished this week.
  • Please drive carefully and observe all posted speed limits.
  • Work hours: 7 a.m.-7:30 p.m., weekend work. Construction lights will be used.

Work Zone Cameras and 511:

Driving piling to support the work bridge used to construct the new eastbound bridge.

Driving piling to support the work bridge used to construct the new eastbound bridge.

February 6, 2023

Activities:

  • It’s nearly time for bridge and roadway construction!
  • Work hours: 7 a.m.-7:30 p.m., weekend work, weather dependent. Construction lights will be used.
  • Please drive carefully and observe all posted speed limits.

Work Zone Cameras and 511:

Preassembling the steel reinforcing cages that will be cast in one of the new concrete pier support beams.

Preassembling the steel reinforcing cages that will be cast in one of the new concrete pier support beams.

January 30, 2023

Activities:

  • Construction has resumed on the work bridge to support eastbound bridge construction.
  • Maintaining two lanes of traffic on the east and westbound roadways.
  • Weekend work continues, work hours: 7 a.m.-7:30 p.m., weather dependent. Construction lights will be used.
  • Please drive carefully and observe all posted speed limits.

Work Zone Cameras and 511:

Assembling the steel reinforcing cages that will be used for the new eastbound bridge piers.

Assembling the steel reinforcing cages that will be used for the new eastbound bridge piers.

January 23, 2023

Activities:

  • Construction has resumed on the work bridge to support eastbound bridge construction.
  • Maintaining two lanes of traffic on the east and westbound roadways.
  • Weekend work continues, work hours: 7 a.m.-7:30 p.m., weather dependent. Construction lights will be used.
  • Please drive carefully and observe all posted speed limits.

Work Zone Cameras and 511:

The east end of COULSON PARK at the Yellowstone River, including fishing access, is closed due to construction. Charlene Street access will be limited to construction-related traffic at the west parking area.

The east end of COULSON PARK at the Yellowstone River, including fishing access, is closed due to construction. Charlene Street access will be limited to construction-related traffic at the west parking area.

January 17, 2023

Activities:

  • Construction has resumed on the work bridge to support eastbound bridge construction.
  • Maintaining two lanes of traffic on the east and westbound roadways.
  • Weekend work starting again, work hours: 7 a.m.-7:30 p.m., weather dependent.
  • Please drive carefully and observe all posted speed limits.

Work zone cameras:

Disassembling the 2022 work bridge and relocating to support eastbound bridge construction.

Disassembling the 2022 work bridge and relocating to support eastbound bridge construction.

January 9, 2023

Activities:

  • Maintaining two lanes of traffic on the east and westbound roadways.
  • During the winter season please slow down, drive carefully, and observe all posted speed limits.
  • General work hours: 7 a.m.-5 p.m., weather dependent, no weekend work.

Construction:

Under the new bridge

Under the new bridge

December 19, 2022 – January 2, 2023

Activities:

  • Maintaining two lanes of traffic on the east and westbound roadways.
  • During the winter season please slow down, drive carefully, and observe all posted speed limits.
  • General work hours: 7 a.m.-5 p.m., weather dependent, no weekend work.

Construction:

Reinforcing steel for the eastbound bridge drill shafts by Grizzly Steel.

Reinforcing steel for the eastbound bridge drill shafts by Grizzly Steel.

December 5-18, 2022

Activities:

  • Maintaining two lanes of traffic on the east and westbound roadways.
  • During the winter season please slow down, drive carefully, and observe all posted speed limits.
  • General work hours: 7 a.m.-5 p.m., weather dependent, no weekend work.

Construction:

Moving the work bridge – preparing for 2023 construction.

Moving the work bridge – preparing for 2023 construction.

November 18, 2022

Activities:

  • HAPPY THANKSGIVING! Limited work days this holiday week.
  • Switched to two lanes of traffic on the east and westbound roadways.
  • During the winter season please slow down, drive carefully, and observe all posted speed limits.
  • General work hours are: 7 a.m.-5 p.m., weather dependent, no weekend work.

Construction:

Winter is here! Let’s keep each other safe.

Winter is here! Let’s keep each other safe.

November 14, 2022

Activities:

  • Switching to one lane of traffic each on the east and westbound roadways, likely lasting through Thanksgiving.
  • WATCH for changing traffic patterns.
  • Winter is here! Please slow down, drive carefully, and observe all posted speed limits. Let’s keep each other safe.
  • In general work hours are: 7 a.m.-7 p.m., weather dependent, limited weekend work.

Construction:

Sign Placement (and racing the weather!)

Sign Placement (and racing the weather!)

November 7, 2022

11/11/2022. Veterans, thank you for the sacrifices you have made on our behalf. Thank you for your service.
-The I 90 Yellowstone Billings Construction Team

Activities:

  • Two-way traffic and the utilization of the crossovers will end on or before November 14. Single lane closures in both directions will be utilized throughout the project.
  • WATCH for changing traffic patterns.
  • General work hours are: 7 a.m.-7 p.m., weather dependent, limited weekend work.

Construction:

Restrictions:

  • Width restrictions for loads 13 feet and over will end for the winter before or during the Veteran’s Day weekend.
Traffic Barrier Construction

Traffic Barrier Construction

October 31, 2022

Activities:

  • The westbound lane has limited shoulders. Please slow down.
  • In general work hours are: 7:00 a.m.-7:00 p.m., 7-days/week, weather dependent.
  • Zipper merging continues. Be courteous to merging drivers.
  • UPCOMING Next Week: One lane of traffic each direction separated by a barrier.

Construction:

Restrictions:

  • Width restrictions in place for loads 13’ and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area M-F, 3:30-5:30 a.m. Please plan ahead.

Special Request:
Please do NOT stop in the work zone to take photos or video. This includes the bridge and shoulders areas on the interstate. Help us keep drivers and construction workers safe!

New Pavement

New Pavement

October 24, 2022

Activities:

  • The 27th Street westbound off-ramp will be opened this weekend, weather dependent.
  • The westbound lane has limited shoulders. Please slow down.
  • In general work hours are: 7:00 a.m.-7:00 p.m., 7-days/week, weather dependent.
  • Zipper merging continues. Be courteous to merging drivers.

Construction:

Restrictions:

  • Width restrictions in place for loads 13’ and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area M-F, 3:30-5:30 a.m. Please plan ahead.

Special Request:
Please do NOT stop in the work zone to take photos or video. This includes the bridge and shoulders areas on the interstate. Help us keep drivers and construction workers safe!

New Westbound Bridge Deck

New Westbound Bridge Deck

October 17, 2022

Activities:

  • The 27th Street westbound off-ramp is closed and tentatively will be opened this weekend, weather dependent.
  • The westbound lane has limited shoulders. Please slow down.
  • In general work hours are: 7:00 a.m.-7:00 p.m., 7-days/week, weather dependent.
  • Zipper merging continues. Be courteous to merging drivers.

Construction:

Restrictions:

  • Width restrictions in place for loads 13’ and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area M-F, 3:30-5:30 a.m. Please plan ahead.

Special Request:
Please do NOT stop in the work zone to take photos or video. This includes the bridge and shoulders areas on the interstate. Help us keep drivers and construction workers safe!

Westbound Talen Energy Rail Spur Structure – Nearly Finished!

Westbound Talen Energy Rail Spur Structure – Nearly Finished!

October 10, 2022

Activities:

  • The 27th Street westbound off-ramp will be closed for two weeks starting Monday, October 10, 2022.
    • Day and night work are planned to expedite the construction.
    • No-glare lights will be used.
  • The new westbound lane has limited shoulders. Please slow down.
  • In general work hours are: 7:00 a.m.-7:00 p.m., 7-days/week, weather dependent.
  • Zipper merging continues. Be courteous to merging drivers.

Construction:

With this project, we are improving your driving experience. Project improvements will extend pavement life, enhance roadway features, and reduce maintenance costs. Thanks again for your patience during construction. – Mike Anderson, Sletten Construction Manager

Restrictions:

  • Width restrictions in place for loads 13’ and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area M-F, 3:30-5:30 a.m. Please plan ahead.

Special Request:
Please do NOT stop in the work zone to take photos or video. This includes the bridge and shoulders areas on the interstate. Help us keep drivers and construction workers safe!

27th Street Westbound Off-ramp

27th Street Westbound Off-ramp

October 3, 2022

Activities:

  • The final pour for the bridge’s concrete deck is scheduled for 10/3.
    • Night work and use of no-glare lights will be used.
    • There will be increased concrete truck traffic, drive cautiously.
  • The new westbound lane has limited shoulders. Please slow down.
  • In general work hours are: 7:00 a.m.-7:00 p.m., 7-days/week, weather dependent.
  • Zipper merging continues. Be courteous to merging drivers.

Construction:

Restrictions:

  • Width restrictions in place for loads 13’ and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area M-F, 3:30-5:30 a.m. Please plan ahead.

Special Request:
Please do NOT stop in the work zone to take photos or video. This includes the bridge and shoulders areas on the interstate. Help us keep drivers and construction workers safe!

Bridge work continues – pouring the concrete deck.

Bridge work continues – pouring the concrete deck.

September 26, 2022

Activities:

  • The bridge’s concrete deck will be poured 9/26, 9/29, and 10/3.
    • Night work and use of no-glare lights will be used.
    • There will be increased concrete truck traffic during pours, drive cautiously.
  • The new westbound lane has limited shoulders. Please slow down.
  • In general work hours are: 7:00 a.m.-7:00 p.m., 7-days/week, weather dependent.
  • Zipper merging continues. Be courteous to merging drivers.

Construction:

Restrictions:

  • Width restrictions in place for loads 13’ and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area M-F, 3:30-5:30 a.m. Please plan ahead.

Special Request:
Please do NOT stop in the work zone to take photos or video. This includes the bridge and shoulders areas on the interstate. Help us keep drivers and construction workers safe!

Bridge work continues in preparation for pouring the concrete deck

Bridge work continues in preparation for pouring the concrete deck

September 19, 2022

Activities:

  • Night work and use of construction lights will occur several times, 9/26-10/3, while the bridge concrete deck is poured.
  • The new westbound lane has limited shoulders. Please slow down.
  • Work hours: 7:00 a.m.-7:00 p.m., 7-days/week, weather dependent.
  • Zipper merging continues. Please be courteous.

Construction:

Restrictions:

  • Width restrictions in place for loads 13’ and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area M-F, 3:30-5:30 a.m. Please plan ahead.

Special Request:
Please do NOT stop in the work zone to take photos or video. This includes the bridge and shoulders areas on the interstate. Help us keep drivers and construction workers safe!

Work continues on the westbound river bridge

Work continues on the westbound river bridge

September 12, 2022

Activities:

  • Night work is possible during the last two weeks of September.
  • The new westbound lane has limited shoulders. Please slow down.
  • Work hours: 7:00 a.m.-7:00 p.m., 7-days/week, weather dependent.
  • Zipper merging continues. Please be courteous.

Construction:

Restrictions:

  • Width restrictions in place for loads 13’ and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area M-F, 3:30-5:30 a.m. Please plan ahead.

Special Request:
Please do NOT stop in the work zone to take photos or video. This includes the bridge and shoulders areas on the interstate. Help us keep drivers and construction workers safe!

New Westbound Bridge Steel Beam and Deck Work

New Westbound Bridge Steel Beam and Deck Work

September 5, 2022

Activities:

  • No construction work over the holiday weekend, Friday afternoon or Saturday-Monday.
  • The new westbound lane has limited shoulders. Please slow down.
  • Work hours: 7:00 a.m.-7:00 p.m., weather dependent.
  • Zipper merging continues. Please be courteous.

Construction:

Restrictions:

  • Width restrictions in place for loads 13’ and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area M-F, 3:30-5:30 a.m. Please plan ahead: No wide load escorts, Monday, September 5, NO EXCEPTIONS.

Special Request:
Please do NOT stop in this work zone to take photos or video. This includes the bridge and shoulders areas on the interstate. Help us keep drivers and construction workers safe with room to work!

Have a safe and happy Labor Day!

Westbound Talen Energy Rail Spur Bridge Arch

Westbound Talen Energy Rail Spur Bridge Arch

August 29, 2022

Construction:

Activities:

  • Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes until November 2022.
  • The new westbound lane has limited shoulders. Please slow down.
  • Work hours: 7:00 a.m.-7:00 p.m., seven days a week, weather dependent.
  • Zipper merging continues. Please be courteous.

Restrictions:

  • Width restrictions in place for loads 13’ and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area M-F, 3:30-5:30 a.m. Please plan ahead: No wide load escorts, Monday, September 5, NO EXCEPTIONS.

Special Request:
Please do NOT stop in this work zone to take photos or video. This includes the bridge and shoulders areas on the interstate. Help us keep drivers and construction workers safe with room to work!

Have a safe and happy Labor Day!

Work on the Talen Energy Rail Spur Bridge Arch

Work on the Talen Energy Rail Spur Bridge Arch

August 22, 2022

Construction:

Activities:

  • Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes until November 2022.
  • The new westbound lane has limited shoulders. Please slow down.
  • Work hours: 7:00 a.m.-7:00 p.m., seven days a week, weather dependent.
  • Zipper merging continues. Please be courteous.

Restrictions:

  • Width restrictions in place for loads 13’ and over.
  • Wide load accommodations and a staging area have been provided.
  • Trucks are being guided through the area M-F, 3:30-5:30 a.m. Please plan ahead: No wide load escorts, Mon., September 5, no exceptions.

Special Request:
Please do NOT stop in this work zone to take photos or video. This includes the bridge and shoulders areas on the interstate. Help us keep drivers and construction workers safe with room to work!

Westbound bridge construction

Westbound bridge construction

August 15, 2022

Construction Work: Work on the new westbound river bridge continues. The bridge substructure has been completed! Other westbound bridge work includes steel bridge beam fabrication, erection, and deck formation (after which the deck will be placed).

The new westbound Talen Energy Rail Spur Bridge is being reconstructed. Currently, we are backfilling the arch foundation and installing permanent retaining walls in preparation for arch section setting, which should occur the week of 8/15.

We now have two project camera views, visit: I90 Yellowstone River Project Billings - Project Camera | Montana Department of Transportation (MDT) or SCAN Web 6.0 - Camera.

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. Daytime operations are generally seven days/week from 7:00 a.m.-7:00 p.m., weather dependent. Zipper merging in the project area continues, and we encourage drivers to be safe and courteous as lanes merge.

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.

Special Request: For your safety and the safety of our construction workers, do NOT stop in the I 90 Yellowstone River Project, Billings, work zone to take photos or video. This includes areas on the bridge and interstate shoulders. Help us keep drivers and construction workers safe! Thank you for slowing down, paying attention, and giving our crews space to safely work.

Erecting the steel beams for the new westbound river bridge

Erecting the steel beams for the new westbound river bridge.

August 8, 2022

Construction Work: Update for this weekend: limited weekend work (August 6-7, 2022).

The new westbound Talen Energy Rail Spur Bridge is being reconstructed. Currently, we are backfilling the arch foundation and installing permanent retaining walls in preparation for arch section setting, which should occur the week of 8/15.

Work on the new westbound river bridge continues with completion of the substructure! Other westbound bridge work includes steel bridge beam fabrication and erection, after which the deck will be placed.

We now have two project camera views, visit: I90 Yellowstone River Project Billings - Project Camera | Montana Department of Transportation (MDT) or SCAN Web 6.0 - Camera.

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. Daytime operations are generally seven days/week from 7:00 a.m.-7:00 p.m., weather dependent. Zipper merging in the project area continues, and we encourage drivers to be safe and courteous as lanes merge.

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.

Special Request: For your safety and the safety of our construction workers, do NOT stop in the I 90 Yellowstone River Project, Billings, work zone to take photos or video. This includes areas on the bridge and interstate shoulders. Help us keep drivers and construction workers safe! Thank you for slowing down, paying attention, and giving our crews space to safely work.

Erecting the steel girders for the new westbound bridge

August 1, 2022

Construction Work: The new westbound Talen Energy Rail Spur Bridge is being reconstructed. Currently, we are backfilling the arch foundation and installing permanent retaining walls in preparation for arch section setting. Work on the new westbound river bridge continues with steel bridge beam fabrication and erection in progress, and bridge deck forming and reinforcing to occur as steel erection progress allows. View the project camera.

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. Daytime operations are generally seven days/week from 7:00 a.m.-7:00 p.m., weather dependent. Zipper merging in the project area continues, and we encourage drivers to be safe and courteous as lanes merge.

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.

Special Request: For your safety and the safety of our construction workers, do NOT stop in the I 90 Yellowstone River Project, Billings, work zone to take photos or video. This includes areas on the bridge and interstate shoulders. Help us keep drivers and construction workers safe! Thank you for slowing down, paying attention, and giving our crews space to safely work.

hot air baloon

July 25, 2022

Construction Work: The project work bridge was damaged during the June flooding event, but has been repaired. Work on the I 90 westbound bridge has resumed.
NOTE: the work bridge is designed and built to support crews and equipment during construction of the new bridges.

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. Daytime operations are generally seven days/week from 7:00 a.m.-7:00 p.m., weather dependent. Zipper merging in the project area continues, and we encourage drivers to be safe and courteous as lanes merge.

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.

Special Request: Drivers are using the “zipper merge” method while merging into one lane in both the east- and westbound lanes throughout the I 90 Yellowstone River Project, Billings, work zone. Zipper merging is the safest, quickest, and most courteous way to merge. When traffic is congested and a lane is closed ahead, drivers wait until a designated merge point to take turns moving into the open lane like a zipper.

be a zipper

July 18, 2022

Construction Work: Zipper merging in the project area begins 7/18/22. The project work bridge was damaged during the June flooding event. Due to the high-water level and safety concerns for the construction crews, MDT and the construction contractor were not able to ascertain the damage to the work bridge until recently. The project team is currently fixing the work bridge and we will have updates next week. Work on the I 90 westbound bridge continues but minor delays are expected.
NOTE: the work bridge is designed and built to support crews and equipment during construction of the new bridges.

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. Daytime operations are generally seven days/week from 7:00 a.m.-7:00 p.m., weather dependent.

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.

Special Request: For your safety and the safety of our construction workers, do NOT stop in the I 90 Yellowstone River Project, Billings, work zone to take photos or video. This includes areas on the bridge and interstate shoulders. Help us keep drivers and construction workers safe! Thank you for slowing down, paying attention, and giving our crews space to safely work.

be a zipper

Drivers will be asked to use the “zipper merge” method while merging into one lane in both the east- and westbound lanes throughout the I 90 Yellowstone River Project, Billings, work zone. Zipper merging is the safest, quickest, and most courteous way to merge. When traffic is congested and a lane is closed ahead, drivers wait until a designated merge point to take turns moving into the open lane like a zipper.

July 11, 2022

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. Daytime operations are generally seven days/week from 7:00 a.m.-7:00 p.m., weather dependent.

Construction Work: Zipper merging in the project area begins 7/18/22. Due to the June flooding event, the schedule for the westbound Yellowstone River bridge has been reorganized but work continues.

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.

Special Request: For your safety and the safety of our construction workers, do NOT stop in the I 90 Yellowstone River Project, Billings, work zone to take photos or video. This includes areas on the bridge and interstate shoulders. Help us keep drivers and construction workers safe! Thank you for slowing down, paying attention, and giving our crews space to safely work.

Man wearing a seatbelt.

DID YOU KNOW…
Seatbelts have been around since 1885. That’s 137 YEARS!
Commit to always buckling up before you go.
Let’s ride in style like those who traveled before us.

July 4, 2022

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. Daytime operations are generally seven days/week from 7:00 a.m.-7:00 p.m., weather dependent.
Note: No construction work starting July 1 (midday) through July 4, 2022..

Construction Work: Asphalt paving of the westbound lane between the new Yellowstone River bridge and Talen structure has been completed. Due to the June flooding event, the schedule for the westbound Yellowstone River bridge has been reorganized but work continues.

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.
Note: NO OVERSIZE ESCORTS Monday, July 4, 2022..

Special Request: For your safety and the safety of our construction workers, do NOT stop in the I 90 Yellowstone River Project, Billings, work zone to take photos or video. This includes areas on the bridge and interstate shoulders. Help us keep drivers and construction workers safe! Thank you for slowing down, paying attention, and giving our crews space to safely work.

From our family to yours, happy 4th of July! Buckle up, drive sober, and enjoy the festivities

June 27, 2022

Special Request:

For your safety and the safety of our construction workers, do NOT stop in the I 90 Yellowstone River Project, Billings, work zone to take photos or video. This includes areas on the bridge and interstate shoulders. Help us keep drivers and construction workers safe! Thank you for slowing down, paying attention, and giving our crews space to safely work.

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. Daytime operations are generally seven days/week from 7:00 a.m.-7:00 p.m., weather dependent.
Note: No construction work July 2-4, 2022..

Construction Work: Asphalt paving of the westbound lane between the new Yellowstone River bridge and Talen structure has been completed. Due to the June flooding event, the schedule for the westbound Yellowstone River bridge has been reorganized but work continues.

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.
Note: NO OVERSIZE ESCORTS Monday, July 4, 2022.

yellowstone river

June 20, 2022

Special Request: For your safety and the safety of our construction workers, do NOT stop in the work zone to take photos or video including on the bridge or project shoulders. Thank you!

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. Daytime operations are generally seven days/week from 7:00 a.m.-7:00 p.m., weather dependent.
Note: No construction work July 2-4, 2022.

Construction Work: Asphalt paving of the westbound lane between the new Yellowstone River bridge and Talen structure continues. Due to the flooding, work on the westbound Yellowstone River bridge is on hold while engineers inspect the work bridge. We’ll update you when we have more information.

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.
Note: NO OVERSIZE ESCORTS Monday, July 4, 2022.

June 13, 2022

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. Daytime operations are now seven days/week from 7:00 a.m.-7:00 p.m., weather dependent.

Construction Work: The new westbound Talen Energy Rail Spur Bridge is being reconstructed. Currently steel piling is being installed, which will serve as the structure foundation. The new westbound river bridge foundations are still being constructed, including installing formwork and reinforcing steel cages for the bridge substructure, and continuing to pour concrete for the drilled shaft pier foundations. Asphalt paving of the westbound lane between the new Yellowstone River bridge and Talon structure has started!

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.

bridge

Safety tips for the traveling public!

  • Drive Sober
  • Buckle Up
  • Slow Down
  • Stay Alert
  • Share the Road
  • Secure your Load
  • Expect the Unexpected

May 23 - June 5, 2022

Activities: Construction update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Daytime operations are seven days/week from 7:00 a.m.-7:00 p.m., weather dependent. Note: No construction work will occur over the Memorial Day weekend, May 28-30.

Construction Work:

The new westbound Talen Energy Rail Spur Bridge is being reconstructed. Currently steel piling is being installed, which will serve as the structure foundation. The new westbound river bridge foundations are still being constructed, including installing formwork and reinforcing steel cages for the bridge substructure, and continuing to pour concrete for the drilled shaft pier foundations.

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m. No wide load escorts on Memorial Day.

Drivers are reminded to wear your seat belt, don’t drive distracted, and put your phone down please! Maintain posted speeds and no stopping or slowing in travel lanes unless it is an emergency. Please be alert to new traffic patterns and expect short delays.

Construction of Westbound River Bridge Foundations

Construction of Westbound River Bridge Foundations

May 16, 2022

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Daytime operations are now seven days/week from 7:00 a.m.-7:00 p.m., weather dependent. Note: No construction work over Memorial Day weekend, May 28-30.

Construction Work:

The new westbound Talen Energy Rail Spur Bridge is being reconstructed. Currently steel piling is being installed which will serve as the structure foundation. The new westbound river bridge foundations are still being constructed, including

  • installing formwork and reinforcing steel cages for the bridge substructure, and
  • continuing to pour concrete for the drilled shaft pier foundations.

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.

Drivers are reminded to wear your seat belt, don’t drive distracted, and put your phone down please! Maintain posted speeds and no stopping or slowing in travel lanes unless it is an emergency. Please be alert to new traffic patterns and expect short delays.

Placing Concrete for the Bridge Pier Columns

Placing Concrete for the Bridge Pier Columns

May 9, 2022

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Daytime operations are now seven days/week from 7:00 a.m.-7:00 p.m., weather dependent.

Construction Work:

The new westbound Talen Energy Rail Spur Bridge is being reconstructed, and construction of the new westbound bridge foundations is underway, including

  • drilling large holes, just over 6 feet in diameter, deep into the riverbed,
  • installing preassembled reinforcing steel cages into the excavations, and then
  • filling the shafts with concrete.

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.

Drivers are reminded to wear your seat belt, don’t drive distracted, and put your phone down please! Maintain posted speeds and no stopping or slowing in travel lanes unless it is an emergency. Please be alert to new traffic patterns and expect short delays.

I90 Yellowstone River Project Billings Construction April 2022

May 2, 2022

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Daytime operations are now seven days/week from 7:00 a.m.-7:00 p.m., weather dependent.

Construction Work:

The existing westbound Talen Energy Rail Spur Bridge has been removed. Construction of the new westbound bridge foundations is underway, including

  • drilling large holes, just over 6 feet in diameter, deep into the riverbed,
  • installing preassembled reinforcing steel cages into the excavations, and then
  • filling the shafts with concrete.

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.

Drivers are reminded to wear your seat belt, don’t drive distracted, and put your phone down please! Maintain posted speeds and no stopping or slowing in travel lanes unless it is an emergency. Please be alert to new traffic patterns and expect short delays.

April 25, 2022

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has a limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Daytime operations are now seven days/week from 7:00 a.m.-7:00 p.m., weather dependent.

Construction Work:

  • The existing westbound Talen Energy Rail Spur Bridge is currently being removed. Construction of the new westbound bridge foundations is underway, including
    • drilling large diameter holes deep into the ground,
    • installing preassembled reinforcing steel cages into the excavated holes, and then
    • filling the holes with concrete.

Restrictions: Width restrictions are in place for loads 13 feet and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.

Drivers are reminded to wear your seat belt, don’t drive distracted, and put your phone down please! Maintain posted speeds and no stopping or slowing in travel lanes unless it is an emergency. Please be alert to new traffic patterns and expect short delays.

We Remember graphic

We remember our loved ones, our friends, our neighbors.

Drive every day to protect those who work to serve our road systems. Let’s keep them safe.

April 18, 2022

Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Daytime operations are now seven days/week from 7:00 a.m.-7:00 p.m., weather dependent. No work Easter Sunday.

Construction Work:

  • The existing westbound bridge over the Yellowstone River has been 100% removed.
  • Construction of the new westbound bridge foundations are underway including:
    • Drilling large diameter holes deep into the ground.
    • Installing preassembled reinforcing steel cages into the excavated holes.
    • Then filling the holes with concrete.
  • The existing westbound Talen Energy Rail Spur Bridge is currently being removed.

Restrictions: Width restrictions are in place for loads 13 ft and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.

Drivers are reminded to wear your seat belt, don’t drive distracted, and put your phone down please! Maintain posted speeds and no stopping or slowing in travel lanes unless it is an emergency. Please be alert to new traffic patterns and expect short delays.

NWA

A work zone crew member maintains duties that place him or her within the right-of-way of a street or highway.

Drive every day to protect those who work to serve our road systems. Let’s keep them safe.

April 11, 2022

Current Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. Maintain posted speeds and no stopping or slowing in either lane is advised. Daytime operations are now seven days/week from 7:00 a.m.-7:00 p.m. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Please be alert to new traffic patterns and expect short delays!

Restrictions: Width restrictions are in place for loads 13 ft and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

NWA

April is National Work Zone Awareness.

Construction zone workers are your neighbors. Let’s keep them safe.

April 4, 2022

Current Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. Maintain posted speeds and no stopping or slowing in either lane is advised. Daytime operations are now seven days/week from 7:00 a.m.-7:00 p.m. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Please be alert to new traffic patterns and expect short delays!

Restrictions: Width restrictions are in place for loads 13 ft and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

March 28, 2022

Current Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. Maintain posted speeds and no stopping or slowing in either lane is advised. Daytime operations are now seven days/week from 7:00 a.m.-7:00 p.m. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Please be alert to new traffic patterns and expect short delays!

Restrictions: Width restrictions are in place for loads 13 ft and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m. Freight and wide loads are advised to take an alternate route when possible.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

March 21, 2022

Current Activities: :Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Westbound traffic has been detoured through crossovers to a two-way configuration in the eastbound lanes and will remain this way until November 2022. The new westbound lane has limited shoulder because of the temporary concrete barrier in place for your safety and the safety of our work crews. Maintain posted speeds and no stopping or slowing in either lane is advised. Daytime operations are now seven days/week from 7:00 a.m.-7:00 p.m. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Please be alert to new traffic patterns, slow down, and expect short delays!

Restrictions: Width restrictions are in place for loads 13 ft and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m. Freight and wide loads are advised to take an alternate route when possible.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

March 14, 2022

Current Activities: : Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. MDT will detour both westbound lanes through crossovers to a two-way configuration in the eastbound lanes. Daytime operations are now seven days/week from 6:30 a.m.-6:00 p.m. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Please be alert to new traffic patterns, slow down, and expect short delays!

Restrictions: Width restrictions will begin Wednesday, 3/16/22, weather dependent, for loads 13 ft and over. Wide load accommodations and staging areas will be provided, and trucks will be chauffeured through the construction area from 3:30-5:30 a.m. Freight and wide loads are advised to take an alternate route when possible.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

March 7, 2022

Current Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Work continues on the construction work bridge, and, weather dependent, MDT will begin setting up a single lane closure on the eastbound roadway. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Portable lights may be used in the mornings and evenings. Please travel safely.

Upcoming Activities (March 14, 2022): Weather permitting, the westbound lane will be transitioned through crossovers to a two-way configuration in the eastbound lane.

Restrictions: Currently, there are no wide load restrictions.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

February 28, 2022

Current Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Work continues on the construction work bridge, but no roadway or ramp work is planned. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Portable lights may be used in the mornings and evenings. Please travel safely.

Restrictions: Currently, there are no wide load restrictions.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

February 21, 2022

Current Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Work continues on the construction work bridge, but no roadway or ramp work is planned. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Portable lights may be used in the mornings and evenings. Please travel safely.

Restrictions: Currently, there are no wide load restrictions.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

February 14, 2022

Current Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Work continues on the construction work bridge, but no roadway or ramp work is planned. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Portable lights may be used in the mornings and evenings. Please travel safely.

Restrictions: Currently, there are no wide load restrictions.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

February 7, 2022

No Current Activities: No construction work will take place on I 90 between the 27th Street Interchange and Lockwood Interchange. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Please travel safely.

Restrictions: Currently, there are no wide load restrictions.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down.

January 31, 2022

Current Activities: Construction on I 90 between the 27th Street Interchange and Lockwood Interchange will require closure of one westbound lane for one day only and the timing is weather dependent. Pay attention to lane closures and traffic control devices. Portable lights may be used in the mornings and evenings.

The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Please travel safely.

Restrictions: Currently, there are no wide load restrictions.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down.

January 24, 2022

Current Activities: Construction on I 90 between the 27th Street Interchange and Lockwood Interchange will require closure of one eastbound lane Monday and Tuesday, 1/24-25/2022, weather dependent. Pay attention to lane closures and traffic control devices. Portable lights may be used in the mornings and evenings.

The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Please travel safely.

Restrictions: Currently, there are no wide load restrictions.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

January 17, 2022

Current Activities: I 90 construction between the 27th Street Interchange and Lockwood Interchange will require closure of one eastbound lane. Pay close attention to lane closures and traffic control devices. Portable lights may be used in the mornings and evenings.

The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Monday is a state holiday so there will be no construction work. Please travel safely.

Restrictions: Currently, there are no wide load restrictions.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

January 10, 2022

Current Activities: I 90 construction between the 27th Street Interchange and Lockwood Interchange will require the periodic closure of one lane of traffic on the eastbound lanes (work is weather dependent). Pay close attention to lane closures and traffic control devices. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Portable lights may be used in the mornings and evenings. Please travel safely.

Restrictions: Currently, there are no wide load restrictions.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

January 3, 2022

Current Activities: Weekly update for I 90 between the 27th Street Interchange and Lockwood Interchange. Work continues on the construction work bridge, but no roadway or ramp work is planned. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Portable lights may be used in the mornings and evenings. Please travel safely.

Restrictions: Currently, there are no wide load restrictions.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

December 20 & 27, 2021

Current Activities: I 90 construction between the 27th Street Interchange and Lockwood Interchange will require the closure of one lane of traffic on the westbound lanes for two days only (12/20-21/2021). Pay close attention to lane closures and traffic control devices. Portable lights may be used in the mornings and evenings. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. No construction work on 12/24/21 and 12/31/2021. Happy Holidays and please travel safely!

Restrictions: Currently, there are no wide load restrictions.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

December 13, 2021

Current Activities: I 90 construction between the 27th Street and Lockwood Interchanges will require the closure of one lane of traffic on both the eastbound and westbound lanes. Pay close attention to lane closures and traffic control devices. No ramp work is planned. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Portable lights may be used in the mornings and evenings. Weather and daylight hours are changing, so please travel safely.

Restrictions: Currently, there are no wide load restrictions.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

December 6 and 13, 2021

Current Activities: I 90 between 27th Street and Lockwood Interchanges, both east and westbound lanes including all ramps, will be open. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Portable lights may be used in the mornings and evenings. Weather and daylight hours are changing so please travel safely.

Restrictions: Currently, there are no wide load restrictions.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

November 22 and 29, 2021

Current Activities: Both lanes of I 90 eastbound and westbound including all ramps are open. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed due to work below and next to the existing bridges. Portable lights may be used in the mornings and evenings. Weather and daylight hours are changing so please travel safely.

Restrictions: Currently, there are no wide load restrictions.

Drivers are reminded to wear your seat belt, don’t drive impaired, and put your phone down please.

Have a Safe and Happy Thanksgiving!

November 15, 2021

Plan Ahead!

Current Activities: Next week both eastbound lanes of I 90 between the 27th Street and Lockwood Interchanges will open (westbound is currently open). Shoulder work on the eastbound lane near 27th Street is expected. No ramp work is planned. Expect short delays.

Pile driving begins for the temporary work platforms that will be used to construct the new westbound bridge. The Jim Dutcher Trail at the Yellowstone River Bridges remains closed. Portable lights may be used in the mornings and evenings. Weather and daylight hours are changing so please travel safely.

Restrictions: Currently, there are no wide load restrictions.

All drivers are reminded to slow down, follow all posted signs, and watch for crews working in this busy work zone. Always wear your seat belt, don't drive impaired, and put your phone down please.

November 8, 2021

Plan Ahead!

Current Activities: I 90 between 27th Street Interchange and Lockwood Interchange will be open to single-lane traffic, both east and westbound this week. The 27th Street off- and on-ramps will also be open. Expect short delays.

The Jim Dutcher Trail at the Yellowstone River Bridges remains closed. Daytime construction will continue through the weekend. Portable lights may be used in the morning and evening. Tree removal is planned for this week. Weather and daylight hours are changing so please travel safely.

Upcoming activities: Opening two lanes of traffic for both I 90 westbound and eastbound are scheduled for mid-November, weather permitting.

Restrictions: Wide load width restrictions will be lifted the week of November 8, 2021.

All drivers are reminded to slow down, follow all posted signs, and watch for crews working in this busy work zone. Always wear your seat belt, don't drive impaired, and put your phone down please.

November 1, 2021

Current Activities: Plan Ahead! I 90 between 27th Street Interchange and Lockwood Interchange weekly construction update. The I 90 westbound lane accommodates two-way traffic and the westbound 27th Street off-ramp remains open. The eastbound lane and 27th Street on-ramp are closed. Expect short delays.

The Jim Dutcher Trail at the Yellowstone River Bridges remains closed. Daytime construction will continue through the weekend. Portable lights may be used in the morning and evening. Weather and daylight hours are changing so please travel safely.

Restrictions: Width restrictions are in place for loads 13 ft and over. Wide load accommodations and staging areas have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m. Freight and wide loads are advised to take an alternate route when possible.

All drivers are reminded to slow down, follow all posted signs, and watch for crews working in this busy work zone. Always wear your seat belt, don't drive impaired, and put your phone down please.

October 25, 2021

Current Activities: Plan Ahead! I 90 between 27th Street Interchange and Lockwood Interchange currently has single-lane traffic, both east and westbound. Starting October 25, 2021, a change to two-way traffic on the westbound lane and closure of the eastbound lane and 27th Street on-ramp are planned (weather permitting). The westbound 27th Street off-ramp will remain open. Expect short delays.

The Jim Dutcher Trail at the Yellowstone River Bridges remains closed. Construction activities may continue through the weekend, but no night work is immediately planned. Tree removal is planned for this week.

The weather and hours of daylight are changing, please be alert to new traffic patterns and travel safely.

Restrictions: Width restrictions are in place for loads 13 ft and over. Wide load accommodations and staging areas have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m. Freight and wide loads are advised to take an alternate route when possible.

All drivers are reminded to slow down, follow all posted signs, and watch for crews working in this busy work zone. Always wear your seat belt, don't drive impaired, and put your phone down please.

October 19, 2021

Current Activities: Plan Ahead! I 90 between 27th Street Interchange and Lockwood Interchange will be open to single-lane traffic, both east and westbound, the rest of this week. The westbound 27th Street off-ramp is open. Expect short delays.

The Jim Dutcher Trail at the Yellowstone River Bridges remains closed. Construction activities may continue through the weekend, but no night work is immediately planned. Tree removal is planned for this week. Please travel safely.

Upcoming Activities: A change to two-way traffic on the westbound lane and closure of the eastbound lane and 27th Street on-ramp are planned for next week (weather permitting).

All drivers are reminded to slow down, follow all posted signs, and watch for crews working in this busy work zone. Always wear your seat belt, don't drive impaired, and put your phone down please.

October 18, 2021

Current Activities: Plan Ahead! I 90 between 27th Street Interchange and Lockwood Interchange is down to one lane in each direction. Two-way traffic on the eastbound lane and the westbound 27th Street off-ramp should open this week. Two-way traffic on the westbound lane and closure of the eastbound 27th Street on-ramp are planned for this week too (weather permitting). Expect short delays.

The Jim Dutcher Trail at the Yellowstone River Bridges are closed. Construction activities may continue through the weekend, but no night work is immediately planned. Tree removal is also planned for this week. Please travel safely.

Restrictions: Restrictions are in place for loads 13 ft and over. Wide load accommodations and staging areas have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m. Freight and wide loads are advised to take an alternate route when possible.

All drivers are reminded to slow down, follow all posted signs, and watch for crews working in this busy work zone. Always wear your seat belt, don't drive impaired, and put your phone down please.

October 11, 2021

Current Activities: Plan Ahead! I 90 between 27th Street Interchange and Lockwood Interchange is down to one lane in each direction. Two-way traffic on the eastbound lane and closure of the westbound 27th Street off-ramp have occurred but should be open mid-October. Expect short delays. Construction activities may continue through the weekend, but no night work is immediately planned.

Future Activities: Two-way traffic on the westbound lane and closure of the eastbound 27th Street on-ramp are planned for mid-October (weather permitting).

Restrictions: Width restrictions are in place for loads 13 ft and over. Wide load accommodations and a staging area have been provided, and trucks are being chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m. Freight and wide loads are advised to take an alternate route when possible.

All drivers are reminded to slow down, follow all posted signs, and watch for crews working in this busy work zone. Always wear your seat belt, don't drive impaired, and put your phone down please.

October 4, 2021

Current Activities: Plan Ahead! I 90 between 27th Street Interchange and Lockwood Interchange is down to one lane in each direction. Two-way traffic on the eastbound lane and closure of the westbound 27th Street off-ramp have occurred. The 27th Street off-ramp will be open early to mid-October. Expect short delays. The Jim Dutcher Trail at the Yellowstone River Bridges will close early October and will remain closed until the project is complete and a new trail is constructed. Construction activities may continue through the weekend, but no night work is immediately planned. Tree removal is planned for this week.

Future Activities: Two-way traffic on the westbound lane and closure of the eastbound 27th Street on-ramp are planned for mid-October (weather permitting).

Restrictions: Upcoming width restrictions for loads 13 ft and over. Restrictions start at the end of September. Wide load accommodations and a staging area will be provided, and trucks will be chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m. Freight and wide loads are advised to take an alternate route when possible.

All drivers are reminded to slow down, follow all posted signs, and watch for crews working in this busy work zone. Always wear your seat belt, don't drive impaired, and put your phone down please.

September 27, 2021

Current Activities: Plan Ahead! I 90 between 27th Street Interchange and Lockwood Interchange is down to one lane in each direction. Two-way traffic on the eastbound lane and closure of the westbound 27th Street off-ramp are planned for late September (weather permitting). The 27th Street off-ramp will be closed for about 10 days. Expect short delays.

Future Activities: The Jim Dutcher Trail will be closed early October at the Yellowstone River Bridges. Two-way traffic on the westbound lane and closure of the eastbound 27th Street on-ramp are planned in late October (weather permitting).

Restrictions: Upcoming width restrictions for loads 13 ft and over. Restrictions start at the end of September. Wide load accommodations and a staging area will be provided, and trucks will be chauffeured through the construction area Monday-Friday, 3:30-5:30 a.m. Freight and wide loads are advised to take an alternate route when possible.

All drivers are reminded to slow down, follow all posted signs, and watch for crews working in this busy work zone. Always wear your seat belt, don't drive impaired, and put your phone down please.

September 20, 2021

I 90 between 27th Street Interchange and Lockwood Interchange is down to one lane in each direction. Construction for crossover traffic continues. Expect short delays.

Plan ahead: Two-way traffic on the westbound lane and closure of the westbound 27th Street off-ramp are planned in late-September (weather permitting).

Restrictions: There are no wide-load restrictions at this time. Freight and wide loads are advised to take an alternate route when possible.