November 16, 2023

The Montana Department of Transportation (MDT) and Schellinger Construction recently completed the final portion of paving. Crews anticipate that temporary striping will be completed the week of November 13, weather and other factors permitting.

Motorists can expect reduced speeds and single-lane closures. Width, height, and length restrictions are in place. Check 511mt.net for the most up-to-date information.

Work is expected to pause for the winter after temporary striping is complete. Crews will return in 2024 for seal and cover (chip seal) operations and to apply final striping.

October 12, 2023

The Montana Department of Transportation (MDT) and Schellinger Construction expect to begin paving the westbound portion of Interstate 90 (I 90) in mid-October.

Motorists can expect shifting traffic patterns, with traffic along I 90 remaining in a crossover pattern to allow crews space to safely complete this work. Width, height, and length restrictions are in place. Check 511mt.net for the most up-to-date information.

Work is expected to be substantially completed in mid-November, weather and other factors permitting. Crews will return in 2024 for seal and cover (chip seal) operations and to apply final striping.

August 23, 2023

The Montana Department of Transportation (MDT) and Schellinger Construction expect to begin paving the eastbound portion of Interstate 90 (I 90) throughout the project area in the next week. During this work, motorists can expect traffic control in place, and shifting traffic patterns.

Traffic along I 90 will continue to be rerouted in a crossover pattern to allow crews the space to safely complete this work, with width, height, and length restrictions in place. Check 511mt.net for the most up-to-date information.

July 21, 2023

The Montana Department of Transportation (MDT) and Schellinger Construction have fully removed the Interstate 90 (I 90) eastbound abandoned railroad track bridge. Crews are now working to lower the elevation of the roadway.

Traffic along I 90 will continue to be rerouted in a crossover pattern to allow crews the space to safely complete this work, with width, height, and length restrictions in place. Check 511mt.net for the most up-to-date information.

June 30, 2023

The Montana Department of Transportation (MDT) and Schellinger Construction began work last week to remove the abandoned railroad track bridge. The removal is expected to take about four weeks to complete.

Traffic will continue to be rerouted in a crossover pattern to allow crews space to safely complete this work, with width, height, and length restrictions in place. Check 511mt.net for the most up-to-date information.

No work will take place between July 1 and July 4. MDT wishes the public a safe and happy Independence Day.

April 14, 2023

Construction is anticipated to begin the week of April 17th. Work will begin under single-lane closures, with crossovers patterns expected to begin around May 4th.