I 90 Bozeman East logo

May 17, 2024

The Montana Department of Transportation (MDT) and Knife River will be closing the Interstate 90 (I-90) eastbound off-ramp at the Main Street Interchange (Exit 309) the morning of Monday, May 20. This closure is anticipated to last only a few hours, weather and other factors permitting.

This closure will allow crews time to pave the section of I-90 that connects to this off-ramp. MDT will reopen the ramp as soon as the newly placed pavement is safe to drive on.

Motorists are encouraged to seek an alternative route during this time. Allow for extra travel time if this ramp is part of your normal morning commute.

What motorists should expect during construction:

  • Crossover traffic patterns on I-90.
  • Both east and westbound traffic traveling on the same side of I-90.
  • Traffic reduced to one lane in each direction.
  • Flaggers or temporary signals directing traffic at times.
  • Reduced speed limits.
  • Wide load restrictions.

Visit 511mt.net for the most up-to-date information about width restrictions and other traffic conditions.

April 16, 2024

Crews plan to begin removing and replacing the pavement on the Main Street Interchange (Exit 309) ramps the week of April 22.

Each of the ramps will be closed for approximately two days at a time to remove and replace the pavement. The ramps will not be closed simultaneously and will reopen as soon as the new pavement is safe to drive on. The ramp closures are anticipated to take two weeks to complete, weather and unforeseen factors permitting.

Crews are expected to start with the westbound on-ramp. Once work there is complete, they plan to move on to the westbound off-ramp, followed by the eastbound off-ramp, and finally the eastbound on-ramp.

On Interstate 90 (I-90), crews have begun constructing crossovers in the median. These preparations will allow all traffic to travel on the same side of I-90 while paving work is being performed on the opposite side.

Motorists should expect:

  • Crossover traffic patterns on I-90.
  • Both east and westbound traffic traveling on the same side of I-90.
  • Interchange ramp closures.
  • Traffic reduced to one lane in each direction.
  • Flaggers or temporary signals directing traffic at times.
  • Reduced speed limits.
  • Wide loads restrictions at times. Visit 511mt.net for the most up-to-date information.

April 5, 2024

Crews plan to begin removing and replacing the pavement on the Main Street Interchange (Exit 309) ramps the week of April 15.

Each of the ramps will be closed for approximately two days at a time to remove and replace the pavement. The ramps will not be closed simultaneously and will reopen as soon as the new pavement is safe to drive on. The ramp closures are anticipated to take two weeks to complete, weather and unforeseen factors permitting.

On Interstate 90 (I-90), crews will begin constructing crossovers in the median in the coming weeks. These preparations will allow all traffic to travel on the same side of I-90 while paving work is being performed on the opposite side.

Motorists should expect:

  • Crossover traffic patterns on I-90.
  • Both east and westbound traffic traveling on the same side of I-90.
  • Traffic reduced to one lane in each direction.
  • Flaggers or temporary signals directing traffic at times.
  • Reduced speed limits.
  • Wide loads restrictions at times. Visit 511mt.net for the most up-to-date information.