Public Involvement

Great Falls North

Weekly Updates

January 8, 2021

  • The Montana Department of Transportation (MDT) and Schellinger Construction crews have completed the embankment, or foundation soil, placement portion of the US Highway 87 - Great Falls project between Dent Bridge Road and Great Bear Avenue. Thank you for your patience during this process.
  • As you know, embankment was unloaded on both sides of the road this fall and early winter and was left to settle. This will create a solid foundation for road widening work beginning this spring. This spring’s roadwork will introduce both passing lanes and turning lanes throughout this seven-mile stretch. The goal of this project is to increase the flow of traffic and provide safer roadways for all.
  • MDT will inform the public and media as to when full road construction will officially begin next spring. The schedule will be largely dependent upon the weather, as warm and dry conditions are crucial for successful roadway work. Crews anticipate working from spring of 2021 through November of 2021. The majority of roadwork will be completed next year. Then, in 2022, workers will return briefly to finish painting and chip sealing the road.
  • Drivers should not experience any further delays this winter.
  • Please call 406-207-4484 or email Becca at with any questions or to sign up for project updates. Text updates are also available by texting "GREATFALLS NORTH" to 41411.
  • This will be the last update until spring approaches.

Previous Updates

December 18, 2020

  • The Montana Department of Transportation (MDT) and Schellinger Construction are wrapping up US Highway 87 roadwork for the year!
  • This past week, workers have been completing ditch work and placing erosion control within the seven-mile work zone. Starting Saturday, Dec. 19, crews will no longer be present or impacting traffic. Drivers should not experience delays for the remainder of the calendar year.
  • Now that the embankment placement is substantially complete, MDT will allow the foundation soil to settle. Come spring next year, Schellinger equipment and crews will return for much of 2021 to add passing and turn lanes along the route. This road expansion will reduce congestion and create a safe driving experience for travelers.
  • There will be no email update on Friday, Dec. 25 or Friday, Jan. 1. Additional updates are to come in early 2021.
  • Please call 406-207-4484 or email Becca at with any questions or to sign up for project updates. Text updates are also available by texting "GREATFALLS NORTH" to 41411.

December 11, 2020

  • The Montana Department of Transportation (MDT) and Schellinger Construction remind drivers that roadwork is in progress on US Highway 87 through December. MDT is grateful for your patience.
  • The embankment, or foundation soil, placement process is almost complete. As weather permits, workers and equipment will be present on and beside the road for the majority of this month. However, crews are not working the week of December 19 through December 27.
  • Starting next week, crews will no longer be present or impacting traffic on the roadway. However, drivers can anticipate equipment and workers on the sides of the road completing ditch work and placing erosion control within the seven-mile work zone. Drivers should not experience delays.
  • Once embankment placement is complete, MDT will vacate the area to allow the foundation soil to settle. Come spring next year, Schellinger equipment and crews will return to add passing lanes and turn lanes along the route.
  • Further updates will be communicated as this fall’s construction comes to a close.
  • Please call 406-207-4484 or email Becca at with any questions or to sign up for project updates. Text updates are also available by texting "GREATFALLS NORTH" to 41411.

December 4, 2020

  • The Montana Department of Transportation (MDT) and Schellinger Construction crews have resumed work on US Highway 87 north of Great Falls. Workers and equipment will be present through the majority of December to prepare for spring 2021 construction, weather permitting.
  • Embankment, or foundation soil, is being moved and placed on the sides of the road between Dent Bridge Road and just north of Great Bear Avenue in preparation for road widening work in 2021.
  • This week, drivers can anticipate workers and equipment present between Bootlegger Lateral/Black Eagle Road Intersection and mile post four on US Highway 87. Traffic signals with a pilot car will be set up here. Haul trucks will be entering and exiting the highway between Dent Bridge Road and Powerline Road with flaggers present. Crews will move south down the highway as the month continues.
  • Similar to past weeks, drivers will notice signs indicating a reduced speed as they approach either end of the work zone and will experience a minor delay. MDT encourages travelers to be aware of workers and equipment on and beside the roadway. Schellinger crews will be working for the majority of December in order to complete the embankment, or foundation soil, placement for full spring construction.
  • The Montana Department of Transportation is grateful for your patience during this project. The ultimate goal is to create a safer and more efficient roadway. Please reach out anytime with questions.
  • Please call 406-207-4484 or email Becca at with any questions or to sign up for project updates. Text updates are also available by texting "GREATFALLS NORTH" to 41411.

November 27, 2020

  • The Montana Department of Transportation (MDT) and Schellinger Construction crews resume work on US Highway 87 north of Great Falls on Monday, November 30. Workers and equipment will be present through early to mid-December to prepare for spring 2021 construction. Embankment, or foundation soil, will be placed on the sides of the work zone as weather permits.
  • As a reminder, on Monday, crews will resume work north of Great Falls between Bootlegger Lateral/Black Eagle Road Intersection and mile post four on US Highway 87. Traffic signals with a pilot car will be set up in this location. Haul trucks will be entering and exiting the highway between Dent Bridge Road and Powerline Road with flaggers present.
  • During construction, drivers can continue to anticipate stoplights and flaggers to instruct drivers on when to stop and when to wait for a pilot car. Travelers should expect minor delays at these lights. MDT reminds drivers to be mindful of workers and large equipment on and beside the roadway. Further updates will be communicated as crews move the work zone south towards Great Falls.
  • Please call 406-207-4484 or email Becca at with any questions or to sign up for project updates. Text updates are also available by texting "GREATFALLS NORTH" to 41411.

November 20, 2020

  • The Montana Department of Transportation (MDT) and Schellinger Construction crews are pausing construction during Thanksgiving week. Please note, crews will be off the roads and pausing work between Saturday, November 21 through Monday, November 30. Workers and equipment will not be present for the duration of Thanksgiving week but will resume work thereafter.
  • On Monday, Nov. 30, crews will resume work north of Great Falls between Bootlegger Lateral/Black Eagle Road Intersection and mile post four on US Highway 87. Traffic signals with a pilot car will be set up in this location. Haul trucks will be entering and exiting the highway between Dent Bridge Road and Powerline Road with flaggers present.
  • Embankment, or foundation soil, will continue to be moved and placed throughout the seven-mile work zone as weather permits. Schellinger crews now anticipate working on this portion of the project through early to mid-December in preparation for spring 2021 construction. This embankment process will be completed in 2020 as the material needs to settle in order to be worked on effectively next year.
  • During construction, drivers can continue to anticipate stoplights and flaggers to instruct drivers on when to stop and when to wait for a pilot car. Flaggers will be located between Dent Bridge Road and Powerline Road. There will be a traffic signal with a pilot car between Bootlegger Lateral/Black Eagle Road Intersection and mile post four after the holiday week. Travelers should anticipate minor delays at these lights. MDT reminds drivers to be mindful of workers and large equipment on and beside the roadway.
  • Please call 406-207-4484 or email Becca at with any questions or to sign up for project updates. Text updates are also available by texting "GREATFALLS NORTH" to 41411.

November 13, 2020

  • Schellinger Construction is intermittently pausing embankment placement work due to heavy snowfall in the Great Falls area. Where possible, crews are working on the side of US Highway 87 to move snow off of the construction area.
  • The Montana Department of Transportation (MDT) will continue to place embankment, or foundation soil, throughout the seven-mile work zone as weather permits. This means that some days crews and equipment will be out working and other days they will not; all depending on the weather. Similar to last week, Schellinger crews anticipate working on this portion of the project through late November in preparation for spring 2021 construction. MDT will provide an update if this timeframe changes.
  • Each passing week, workers will move further south towards Great Falls. During embankment placing, drivers can anticipate two stoplights with accompanying flaggers to instruct drivers when to stop and wait for a pilot car. Travelers should anticipate minor delays.
  • MDT will begin full road construction in spring of 2021, also weather dependent. This embankment, or foundation soil, will be used to add passing lanes and turning lanes throughout the area.
  • Travelers are encouraged to be cautious when driving and aware of workers, equipment and weather conditions on and near the road. Signage will indicate when and where to slow down. This stretch of road will not be closed this fall. Please feel free to reach out to me with any questions.
  • Please call 406-207-4484 or email Becca at with any questions or to sign up for project updates. Text updates are also available by texting "GREATFALLS NORTH" to 41411.

November 6, 2020

  • Great Falls travelers will continue to experience minor delays on US Highway 87 north of Great Falls. This fall’s roadwork is in preparation for full road construction in the spring of 2021. The Montana Department of Transportation (MDT), in partnership with Schellinger Construction, continues to place embankment, or foundation soil, on both sides of the highway. Currently, crews anticipate working on this portion of the project through late November. MDT will provide an update if this timeframe changes.
  • Drivers will see equipment and workers present between Essex Lane and Dent Bridge Road for another week or two. After this stretch is complete, Schellinger crews will move further south towards Great Falls. The two stoplights with accompanying flaggers, one in each direction of the highway, remain at Essex Lane and Dent Bridge Road intersections. These lights will instruct drivers when to stop and wait for a pilot car. Travelers should anticipate minor delays.
  • As crews place embankment within the work zone, they are also putting down a form of netting or fabric in addition to the foundation soil. This creates additional solidity and strength for the embankment’s stability. It will be left to settle for 180 days this winter. Then, MDT will begin full road construction in spring of 2021.
  • The embankment placement process is preparing the extended roadsides to include turn lanes and passing lanes next year. Roadway expansion is occurring due to increased traffic volumes through the area. The Montana Department of Transportation’s goal with this project is to increase safety and reduce traffic congestion.
  • Please note, an update will be communicated if weather causes a pause in work progress. Travelers are encouraged to be cautious when driving and aware of workers and equipment on and beside the road. Signs will indicate when and where to slow down. This stretch of road will not be closed this fall. Please reach out with any questions.
  • If you have any questions or to sign up for updates, please call 406-207-4484 or email Becca at . You can also sign up for text updates by texting "GREATFALLS NORTH" to 41411.

October 30, 2020

  • Minor roadwork resumes this week on US Highway 87 north of Great Falls. The Montana Department of Transportation (MDT), in partnership with Schellinger Construction, continues to place embankment, or foundation soil, on both sides of the roadway. Earlier this week, crews moved piles of snow to reduce the impacts of it melting on the embankment. Now, crews are continuing roadwork with accompanying traffic controls. At this time, this fall’s minor roadwork is still expected to end late November. MDT will provide an update if this timeframe changes.
  • Crews have returned to the project zone between Essex Lane and Dent Bridge Road on Highway 87. When traveling this route, drivers will notice two stoplights with accompanying flaggers; one headed in each direction of the highway. These lights will instruct drivers when to stop and wait for a pilot car to lead them. Travelers should anticipate minor delays.
  • This entire process of embankment, or foundation soil, placement will occur between Dent Bridge Road and just north of Great Bear Avenue. This seven-mile zone of road-side embankment will be left to settle this winter. The settled foundation soil will provide stabilized ground for the coming passing lanes and turn lanes in spring of 2021. Details about where turn lanes and pass lanes will be located will be communicated prior to construction next year. As a reminder, crews are anticipated to complete this initial embankment, or foundation soil, placement work at the end of November, weather dependent.
  • Updates will be communicated if weather causes another pause in work progress. Travelers are encouraged to be cautious when driving and aware of workers and equipment on and beside the road. Signs will indicate when and where to slow down. This stretch of road will not be closed this fall. MDT appreciates your patience during this project.
  • If you have any questions or to sign up for updates, please call 406-207-4484 or email Becca at . You can also sign up for text updates by texting "GREATFALLS NORTH" to 41411.

October 23, 2020

  • This fall, the Montana Department of Transportation (MDT) in partnership with Schellinger Construction is working to place mounds of embankment, or foundation soil, on both sides of US Highway 87 to support the addition of passing lanes and turn lanes next spring. Currently, construction is paused due to snow and freezing weather conditions in the area. Crews are anticipated to resume work within the next week. At this time, this fall’s minor roadwork is still expected to end late November. MDT will provide an update if this time frame changes.
  • Construction crews will continue working between Essex Lane through Dent Bridge Road on US Highway 87 as soon as possible. As the fall progresses, travelers will notice equipment moving further south down the work zone, towards Great Falls. Once construction resumes, drivers should anticipate two stoplights with accompanying flaggers; one headed in each direction of the highway. These lights will instruct drivers when to stop and wait for a pilot car to lead them. Travelers should anticipate minor delays.
  • This embankment, or foundation soil, placement along the seven-mile stretch of Highway 87 is being left to settle this winter in order for construction crews to build passing lanes and turn lanes along this stretch of road. This expansion is due to the increase in traffic volumes through the area. Specific details about where turn lanes and pass lanes will begin, and end will be communicated prior to construction next year. As a reminder, crews are anticipated to complete this initial embankment, or foundation soil, placement work at the end of November, weather dependent.
  • This week and early next week, roadwork is paused due to weather conditions. Crews are not anticipated to be back on the roadside until the end of October. Travelers are encouraged to be cautious when driving due to wet and freezing road conditions. This stretch of road will not be closed this fall. MDT will return to work on both sides of the roadway likely towards the end of next week.
  • If you have any questions or to sign up for updates, please call 406-207-4484 or email Becca at . You can also sign up for text updates by texting "GREATFALLS NORTH" to 41411.

October 16, 2020

  • The Montana Department of Transportation (MDT) in partnership with Schellinger Construction crews continue to work on the side of US Highway 87 north of Great Falls. Drivers will notice mounds of embankment, or foundation soil, through the end of November 2020 on both sides of the roadway. This embankment will be used to support road widening work occurring in the spring.
  • Construction crews are now working further south on both sides of the US Highway 87 roadway. Travelers will see equipment from Essex Lane up through Dent Bridge Road. Once this section is complete, trucks will continue to move south down the highway, closer to Great Falls. The work zone ends north of Great Bear Avenue.
  • This initial roadwork is occurring in preparation for full road construction in spring of 2021. The embankment, or foundation soil, now on both sides of the roadway, will be used to build a foundation for road expansion work next spring. MDT will create both passing lanes and turn lanes on this stretch of road. Please be prepared for additional information as spring construction approaches. Crews will complete this initial embankment, or foundation soil, placement work at the end of November.
  • This coming week, driver information remains the same as previous weeks. Travelers may experience minor delays when passing through the area. In the construction zone, speeds are reduced to 35 MPH. Drivers will notice flaggers at intersections, including Essex lane, to inform them of pilot car operations controlling traffic. MDT also encourages all travelers to please be cautious of workers and equipment when passing through. There will be signage along the route that will indicate where to slow down. This stretch of road will not be closed this fall. Please see the Hwy 87 site video linked in the sidebar of the Great Falls North webpage.
  • If you have any questions or to sign up for updates, please call 406-207-4484 or email Becca at . You can also sign up for text updates by texting "GREATFALLS NORTH" to 41411.

October 9, 2020

  • As a reminder, the Montana Department of Transportation (MDT) is completing minor road work on US Highway 87 north of Great Falls through the end of November 2020. Drivers should anticipate construction equipment on the sides of the roadway for the next two months. Construction will then be paused, and full roadwork will resume in the spring of 2021.
  • Construction crews are now slowly moving down the east side of the US Highway 87 road to continue work on about a mile and a half of the total work zone just south of Black Horse Lake Road and up through Dent Bridge Road. Once this portion is finished, trucks will continue to move south down the highway, towards Great Falls. The total work zone is about seven miles and ends north of Great Bear Avenue. This work is occurring in preparation for full road construction in spring of 2021. Travelers will notice embankment, or foundation soil, on the sides of the roadway.
  • The embankment, or foundation soil, on the roadside will be left on the sides of the road until next spring in order to stabilize the road for construction. In 2021, Schellinger construction crews will be working to use this stabilized foundation soil to add passing lanes and turn lanes to the Highway. Addressing the growing traffic volume and increasing safety is the goal of this project. MDT will provide more details as this fall’s minor roadwork wraps up and as spring construction approaches.
  • This coming week, driver information remains the same as previous weeks. Travelers may experience minor delays when passing through the area. In the construction zone, speeds are reduced to 35 MPH. Drivers will notice flaggers at intersections along the work zone to inform them of pilot car operations controlling traffic. MDT also reminds travelers to please be cautious of workers and equipment on the sides of the roadway. There will be posted signage along the route that will indicate where to slow down. This stretch of road will not be closed this fall. MDT appreciates your patience and understanding during this roadwork project.
  • If you have any questions or to sign up for updates, please call 406-207-4484 or email Becca at . You can also sign up for text updates by texting "GREATFALLS NORTH" to 41411.

October 2, 2020

  • The Montana Department of Transportation (MDT) will be working on a project on US Highway 87 north of Great Falls through the end of November. In preparation for full construction in spring of 2021, travelers will notice embankment, or foundation soil, on the sides of the roadway.
  • Construction Equipment is now expected to move to the east side of the US Highway 87 road to continue work on about a mile of the total work zone between Black Horse Lake Road and Dent Bridge Road. Once this area is complete, trucks will work their way south down the highway. The total work zone is about seven miles.
  • The embankment, or foundation soil, on the roadside does serve a purpose. This material will be left to settle on the sides of the roadway until next spring in order to stabilize the road for construction. In 2021, Schellinger construction crews will be working to use this stabilized soil in order to add passing lanes and turn lanes to the Highway. Addressing the growing traffic volume is the primary purpose of this project. MDT will provide more details as spring approaches.
  • This coming week, driver information remains the same. Travelers may experience minor delays. In the construction area, speeds are reduced to 35 MPH. Drivers may notice flaggers at intersections along the work zone to inform them of pilot car operations controlling traffic. MDT also reminds travelers to please be aware of workers and equipment on the sides of the roadway. There will also be posted signage along the route that will indicate where to slow down. This stretch of road will not be closed this fall.
  • If you have any questions or to sign up for updates, please call 406-207-4484 or email Becca at . You can also sign up for text updates by texting "GREATFALLS NORTH" to 41411.