The Butte- Silver Bow Community Transportation Safety Plan is scheduled for a six-month time frame. The Transportation Safety Plan began with a kick-off meeting on March 21, 2012, with the final plan anticipated to be completed by August 2012. The Consultant has meet with the community Transportation Safety Advisory Committee (TSAC) and has analyzed available community safety related crash data. TSAC will continue to meet to help in determining priority safety emphasis areas, strategies and action steps in support of implementing the Butte-Silver Bow Community Transportation Safety Plan.

Proposed Work Plan and Timeline

Kickoff Meeting March 21, 2012
Establish Goal and Select Emphasis Areas April
Identify Current Strategies May
Safety Summit June
Draft Plan July
Final Plan August