The majority of work is complete. Final pavement markings will be applied in August.

Truck traffic in Gallatin Canyon is open to through truck traffic. However, MDT advises through trucks to consider using I-15.

Construction and maintenance work on other projects will continue as needed. Please check MDT’s Road Construction and Road Condition Reports before traveling.

Contacts

Jeffrey M. Ebert, P.E.
MDT Butte District Administrator
3751 Wynne Avenue
PO Box 3068
Butte, MT 59702-3068
406.494.9625


Matt Collingwood
MDT Engineering Project Manager
907 Rouse Street
PO Box 1110
Bozeman, MT 59771-1110
406.556.4724
Highway - 191 Gallatin Canyon Project Schedule & Milestones

Big Sky Turn Lanes/Spurs Summer/Fall 2008
West Fork Gallatin Bridge Summer/Fall 2008 and
Spring/Summer 2009
Swan Creek Summer 2008 and
Spring/Summer 2009
Jack Smith Bridge Spring/Summer 2009
Spanish Creek Spring/Summer 2009
Seeding and topsoil May 2010
Finish Asphalt Pavement June 2010
Chip Seal July 2010
Final pavement markings August 2010
Project Completion Fall 2010