Cut Bank Urban Main Street (U.S. Highway 2) Reconstruction Project
NH 1-3(70)255 - UPN 7624000

· Project Focus
· Schedule
· FAQs
· Newsletters/Documents

Cut Bank Urban Main Street (U.S. Highway 2) Reconstruction Project contacts
Jeff Key, P.E.
RPA Project Manager
PO Box 5653
Helena, MT 59604
| 406-447-5000

Steve Prinzing, P.E.
Preconstruction Engineer
MDT Great Falls District
200 Smelter Avenue NE
PO Box 1359
Great Falls, MT 59403-1359
| 406-454-5899

Cut Bank Urban Main Street (U.S. Highway 2) Reconstruction Project

CUT BANK URBAN

Main Street (U.S. Highway 2) Reconstruction Project

Schedule

The Cut Bank - Urban project began in January 2013 and is expected to take three years to develop. The project is tentatively scheduled for construction in 2016, depending on completion of all project development activities and availability of funding.