Traffic Control Update

  • The Montana Department of Transportation (MDT) and Diamond J Construction plan to begin boring city utilities under the railroad on North 7th Street next week. While this work is occurring, the railroad crossing will be closed. The traveling public will need to use an alternate railroad crossing, such as the detour on North 5th Street.
  • North 7th Street from Main Street to Palmer Street has reopened for business access.
  • Starting the week of May 20, North 7th Street from the north side of Washington Street to the River Street intersection is expected to close to traffic while underground work progresses northward. During this closure, the Orr Street intersection will also be closed to all directions of traffic.

Business Access Update

  • The Ugly Mug drive-through access has been restored and will be open during Bucking Horse Sale. Feel free to call ahead or text your pick-up order to 406-874-8459.

Project Overview

The Montana Department of Transportation (MDT) has partnered with Diamond J Construction to make improvements along Montana Highway 59 (MT 59), in Miles City. Construction will begin at the intersection of MT 59 with Main Street and will continue north for approximately two miles, ending just past Secondary Highway 489 (Kinsey Road).

The purpose of this project is to rehabilitate the existing roadway, enhance safety features, and reduce maintenance costs. In addition to the roadway improvements, the City of Miles City will be updating the water main, sewer line, and storm drain on the segment of roadway south of the Yellowstone River. This work will be done in cooperation with MDT’s road construction project to minimize impacts to the public.

Planned improvements include:

  • Reconstruction of the roadway (south of the Yellowstone River bridge).
  • Widening the shoulders and new plant mix surfacing (north of the bridge).
  • New rumble strips (north of the bridge).
  • Replacement of all non-compliant Americans with Disabilities Act (ADA) ramps.
  • Upgrades to existing sidewalks and ADA curb ramps.
  • Upgraded pavement markings, signage, and guardrail.
  • City utility improvements to the water main, sewer line, and stormwater management system (south of the bridge).
Miles City North map

Miles City North Map

North of River Section Illustration of planned project improvements south of the Yellowstone River

Illustration of planned project improvements north of the Yellowstone River

South of River Section Illustration of planned project improvements south of the Yellowstone River

Illustration of planned project improvements south of the Yellowstone River